Energy Projects Near You

Hurcott Copse Solar Farm (10 MW)

Hurcott Copse Solar Farm is a 10 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 March 2015; the record was last updated on 29 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
29 April 2015record last updated
Somersetcouncil area

Planning timeline

DateStage
10 July 2014Application submitted
19 September 2014Planning permission granted
15 December 2014Construction started
20 March 2015Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
29 April 2015
Operator or applicant
Dillington Farms Ltd
Planning authority
Somerset
Planning application reference
14/02977/FUL
Site area
18.5 ha
Address (REPD)
Hurcott Copse, Boxstone Hill, Hurcott, Ilminster, Somerset
Council area (by location)
Somerset
Time to decision
10 weeks
REPD reference
2118

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Parsonage Barn (extension)solar farm7.6operational2.5
Bushfurlong Solar Farmsolar farm5application withdrawn6.1
Langport Farmsolar farm5application withdrawn6.2
Lower Severalls Farmsolar farm10.8operational7.5
Mahe Farm, Dunsham Lanesolar farm18.5refused8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9373, -2.866).