Solar, wind and battery projects near Ilminster (TA19)
22 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TA19 (Somerset): 5 approved but not yet running, 10 operational. The largest live scheme is Merryfield Lane, Ilton Solar Farm (2.2 MW solar farm, approved on 6 December 2023, not yet built), 2.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TA19
Projects of 1 MW and more (17)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Parsonage Barn (extension)solar farm | solar farm | 7.6 | operationalupdated Aug 2013 | Jul 2012 | granted Oct 2012 | Aug 2013 | Somerset | 1.0 |
| Merryfield Lane, Ilton Solar Farmsolar farm | solar farm | 2.2 | approved, not builtupdated Feb 2025 | Mar 2023 | granted Dec 2023 | Feb 2025 | Somerset | 2.3 |
| Hurcott Copse Solar Farmsolar farm | solar farm | 10 | operationalupdated Apr 2015 | Jul 2014 | granted Sep 2014 | Apr 2015 | Somerset | 3.5 |
| Chard Solar Parksolar farm | solar farm | 3 | operationalupdated Apr 2016 | Jul 2015 | granted Oct 2015 | Apr 2016 | Somerset | 5.8 |
| Langport Farmsolar farm | solar farm | 5 | application withdrawnupdated Feb 2012 | — | — | Feb 2012 | Somerset | 6.0 |
| Bushfurlong Solar Farmsolar farm | solar farm | 5 | application withdrawnupdated Jan 2012 | Feb 2011 | — | Jan 2012 | Somerset | 6.2 |
| Goldenhaye Field Solar Farmsolar farm | solar farm | 2 | operationalupdated Jun 2013 | Apr 2011 | granted Aug 2011 | Jun 2013 | Somerset | 6.9 |
| Fordham Grangesolar farm | solar farm | 1.9 | operationalupdated Jun 2026 | Jul 2024 | granted Mar 2025 | Jun 2026 | Somerset | 7.2 |
| Cricket St Thomaswind farm | wind farm | 3.9 | application withdrawnupdated Jun 2011 | — | — | Jun 2011 | Somerset | 7.2 |
| Modus Furniture, Manor Farmrooftop solar | rooftop solar | 1 | approved, not builtupdated Mar 2023 | Dec 2022 | granted Jan 2023 | Mar 2023 | Somerset | 7.7 |
| Coombe Farm, Bean Field Solar Arrayssolar farm | solar farm | 1.8 | approved, not builtupdated Oct 2024 | Jun 2024 | granted Sep 2024 | Oct 2024 | Somerset | 8.0 |
| Lower Coombe Farm (Bean Field)solar farm | solar farm | 1 | operationalupdated May 2013 | Jun 2012 | granted Aug 2012 | May 2013 | Somerset | 8.0 |
| Lower Coombe Farm Solarsolar farm | solar farm | 1 | operationalupdated Aug 2011 | Nov 2010 | granted Jan 2011 | Aug 2011 | Somerset | 8.2 |
| Wambrook Farmsolar farm | solar farm | 4.1 | operationalupdated Mar 2016 | Aug 2014 | granted Nov 2014 | Mar 2016 | Somerset | 8.4 |
| Barleclose Farmsolar farm | solar farm | 1 | refusedupdated Feb 2013 | Oct 2012 | refused Jan 2013 | Feb 2013 | Somerset | 9.3 |
| Helland Meadssolar farm | solar farm | 1.2 | operationalupdated Jul 2015 | Apr 2014 | granted Jun 2014 | Jul 2015 | Somerset | 9.6 |
| Mahe Farm, Dunsham Lanesolar farm | solar farm | 18.5 | refusedupdated Jun 2026 | May 2024 | refused May 2026 | Jun 2026 | Somerset | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Tesco Ilminsterrooftop solar | rooftop solar | 0.2 | refusedupdated Aug 2021 | Jun 2021 | refused Jul 2021 | Aug 2021 | Somerset | 1.1 |
| ADM Protexin, Lopen Headrooftop solar | rooftop solar | 0.2 | approved, not built may be out of dateupdated Nov 2022 | Aug 2022 | granted Sep 2022 | Nov 2022 | Somerset | 6.7 |
| Adm Protexin, Lopen Headrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2025 | May 2025 | granted Jun 2025 | Aug 2025 | Somerset | 6.7 |
| Fordham Grangebattery storage | battery storage | — | operationalupdated Jun 2026 | Jul 2024 | granted Mar 2025 | Jun 2026 | Somerset | 7.2 |
| Mahe Farm, Dunsham Lanebattery storage | battery storage | — | refusedupdated Jun 2026 | May 2024 | refused May 2026 | Jun 2026 | Somerset | 9.9 |
Distance from the average position of the TA19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 15 | 0 | 2 | 9 | 2 | 4 |
| Rooftop solar | 4 | 0 | 3 | 0 | 1 | 1.2 |
| Wind farm | 1 | 0 | 0 | 0 | 0 | 0 |
| Battery storage | 2 | 0 | 0 | 1 | 1 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Somerset decides solar, wind and battery applications
| Applications | Somerset | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 185 | 10,236 |
| Refused | 46 (25%) | 19% |
| Solar refused | 34 of 153 | 12% |
| Onshore wind refused | 9 of 10 | 45% |
| Battery storage refused | 3 of 22 | 16% |
| Median time from submission to decision | 14.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 17 / 9 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TA19, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.