Energy Projects Near You

Parsonage Barn (extension) (7.6 MW solar farm)

Parsonage Barn (extension) is a 7.6 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 28 June 2013; the record was last updated on 16 August 2013.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.6 MWsolar farm
operationalstatus in REPD
16 August 2013record last updated
Somersetcouncil area

Planning timeline

DateStage
27 July 2012Application submitted
18 October 2012Planning permission granted
28 May 2013Construction started
28 June 2013Operational

Project details

Technology
solar farm
Capacity
7.6 MW
Status (REPD)
operational
Record last updated
16 August 2013
Operator or applicant
Private Developer
Planning authority
Somerset
Planning application reference
12/02823/FUL
Address (REPD)
Stocklinch Road, Whitelackington, Ilminster, Somerset
Council area (by location)
Somerset
Time to decision
12 weeks
REPD reference
1606

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hurcott Copse Solar Farmsolar farm10operational2.5
Langport Farmsolar farm5application withdrawn5.9
Bushfurlong Solar Farmsolar farm5application withdrawn6.0
Mahe Farm, Dunsham Lanesolar farm18.5refused9.4
Lower Severalls Farmsolar farm10.8operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9355, -2.9022).