Caswell Farm Solar Park (6.7 MW)

Caswell Farm Solar Park is a 6.7 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 March 2016; the record was last updated on 31 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.7 MWsolar farm
operationalstatus in REPD
31 August 2016record last updated
Dorsetcouncil area

Planning timeline

DateStage
8 March 2013Application submitted
13 December 2013Planning permission granted
23 January 2016Construction started
23 March 2016Operational

Project details

Technology
solar farm
Capacity
6.7 MW
Status (REPD)
operational
Record last updated
31 August 2016
Operator or applicant
Juwi Renewable Energies
Planning authority
Dorset
Planning application reference
1/D/13/000242
Site area
19.2 ha
Address (REPD)
Caswell Farm, Common Lane, Ryme Intrinseca, Sherborne, Dorset
Council area (by location)
Dorset
Time to decision
40 weeks
REPD reference
1898

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Caswell Farm, Common Lane Solar Farmsolar farm40application submitted0.6
Caswell Farm, Common Lanebattery storage20application submitted0.6
Clifton Farmsolar farm35operational2.2
Alton Mead Lanesolar farm5permission expired2.8
Higher Stockbridge Farmsolar farm35approved, not built5.7
Camp Road, West Cokersolar farm15.2approved, not built7.5
Southern Counties Shooting Ground Phase 2solar farm5operational7.8
Southern Counties Shooting Ground Phase 1solar farm9operational7.9
Rampisham Northsolar farm5operational9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8878, -2.5962).