Energy Projects Near You

Higher Stockbridge Farm (35 MW solar farm)

Higher Stockbridge Farm is a 35 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 December 2021, not yet built; the record was last updated on 12 September 2023. REPD records the planning permission as expiring on 8 December 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWsolar farm
approved, not builtmay be out of datestatus in REPD
12 September 2023record last updated
Dorsetcouncil area

REPD records the planning permission as expiring on 8 December 2024, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
23 December 2019Application submitted
8 December 2021Planning permission granted
8 December 2024Permission expired

Project details

Technology
solar farm
Capacity
35 MW
Status (REPD)
approved, not built
Record last updated
12 September 2023
Operator or applicant
Voltalia UK
Planning authority
Dorset
Planning application reference
WD/D/19/003181
Site area
79.0 ha
Address (REPD)
Higher Stockbridge Farm, Stockbridge, Sherborne
Council area (by location)
Dorset
Time to decision
102 weeks
Contracts for Difference
AR4
REPD reference
7817

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Alton Mead Lanesolar farm5permission expired3.5
Caswell Farm, Common Lane Solar Farmsolar farm40application submitted5.1
Caswell Farm, Common Lanebattery storage20application submitted5.1
Caswell Farm Solar Parksolar farm6.7operational5.7
Clifton Farmsolar farm35operational5.9
North Dairy Farm Solar Farmsolar farm30approved, not built8.4
Southern Counties Shooting Ground Phase 2solar farm5operational8.9
Southern Counties Shooting Ground Phase 1solar farm9operational9.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8985, -2.5169).