Energy Projects Near You

North Dairy Farm Solar Farm (30 MW)

North Dairy Farm Solar Farm is a 30 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 January 2024, not yet built; the record was last updated on 30 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
approved, not builtstatus in REPD
30 June 2026record last updated
Dorsetcouncil area

Planning timeline

DateStage
15 April 2021Application submitted
15 January 2024Planning permission granted
15 January 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
30 June 2026
Operator or applicant
British Solar Renewables
Planning authority
Dorset
Planning application reference
P/FUL/2021/01018
Site area
77.3 ha
Address (REPD)
North Dairy Farm Access To Nor, Pulham, Dorchester
Council area (by location)
Dorset
Time to decision
144 weeks
Contracts for Difference
AR6
REPD reference
14508

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Higher Stockbridge Farmsolar farm35approved, not built8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8725, -2.4048).