Caswell Farm, Common Lane (20 MW battery storage)

Caswell Farm, Common Lane is a 20 MW battery storage project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 19 August 2025, no decision recorded; the record was last updated on 24 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWbattery storage
application submittedstatus in REPD
24 October 2025record last updated
Dorsetcouncil area

Planning timeline

DateStage
19 August 2025Application submitted

Project details

Technology
battery storage (co-located with re)
Capacity
20 MW
Status (REPD)
application submitted
Record last updated
24 October 2025
Operator or applicant
GridSource Limited
Planning authority
Dorset
Planning application reference
P/FUL/2025/03066
Address (REPD)
Caswell Farm, Common Lane, Ryme Intrinseca, Sherborne
Council area (by location)
Dorset
Name in REPD
Caswell Farm, Common Lane - Battery Energy Storage
REPD reference
19147

Recorded together with Caswell Farm, Common Lane Solar Farm (40 MW solar farm, application submitted).

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Caswell Farm Solar Parksolar farm6.7operational0.6
Alton Mead Lanesolar farm5permission expired2.2
Clifton Farmsolar farm35operational2.5
Higher Stockbridge Farmsolar farm35approved, not built5.1
Southern Counties Shooting Ground Phase 2solar farm5operational7.5
Southern Counties Shooting Ground Phase 1solar farm9operational7.6
Camp Road, West Cokersolar farm15.2approved, not built8.1
Rampisham Northsolar farm5operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8866, -2.5873).