Energy Projects Near You

Land at Stalbridge Park (5 MW solar farm)

Land at Stalbridge Park is a 5 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 23 June 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
23 June 2017record last updated
Dorsetcouncil area

Planning timeline

DateStage
3 July 2015Application submitted
13 October 2015Planning permission granted
4 January 2017Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
23 June 2017
Operator or applicant
British Solar Renewables / NextEnergy Solar Fund (NESF)
Planning authority
Dorset
Planning application reference
2/2015/0898/FUL
Address (REPD)
Land at Stalbridge Park, Landshire Lane, Henstridge, Templecombe, Somerset
Council area (by location)
Dorset
Time to decision
15 weeks
REPD reference
5429

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Bowden Lanesolar farm5operational3.5
Higher Farmsolar farm11refused on appeal5.5
Land at Sutor Farmsolar farm5operational7.1
Brains Solar Farmsolar farm18.8approved, not built7.8
Stour Row Solar Farmsolar farm12permission expired9.1
Hook Valley Solar Parksolar farm17operational9.3
Clapton Farm Solar Parksolar farm5operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9724, -2.3816).