Stour Row Solar Farm (12 MW)

Stour Row Solar Farm is a 12 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 23 August 2014; the record was last updated on 10 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
permission expiredstatus in REPD
10 October 2016record last updated
Dorsetcouncil area

Planning timeline

DateStage
7 June 2011Application submitted
24 August 2011Planning permission granted
23 August 2014Permission expired

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
permission expired
Record last updated
10 October 2016
Operator or applicant
Allied Renewables
Planning authority
Dorset
Planning application reference
2/2011/0713/PLNG
Address (REPD)
Land At St (E) 382383 (N) 120456 Stour Row Shaftesbury Dorset
Council area (by location)
Dorset
Time to decision
11 weeks
REPD reference
6233

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Higher Farmsolar farm11refused on appeal4.3
Hawkers Hill Energy Parkbattery storage20operational4.4
Shaftesbury Energy Parkbattery storage100approved, not built4.4
Fernbrook Solar farm & Battery storagesolar farm49.9approved, not built5.0
Motcombe Road, Motcombe Solar Pv Arrayssolar farm12application submitted5.3
Land east of Littledown Business Parksolar farm6.2operational6.0
Manor Farm (Dorset)solar farm5operational9.1
Land at Stalbridge Parksolar farm5operational9.1