Energy Projects Near You

Fernbrook Solar farm & Battery storage (49.9 MW)

Fernbrook Solar farm & Battery storage is a 49.9 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 13 February 2023, not yet built; the record was last updated on 13 December 2022. REPD records the planning permission as expiring on 13 February 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
13 December 2022record last updated
Dorsetcouncil area

REPD records the planning permission as expiring on 13 February 2026, but the project holds a Contracts for Difference award (AR5), so construction may have started.

Planning timeline

DateStage
2 July 2021Application submitted
25 January 2022Refused by the planning authority
14 June 2022Appeal lodged
13 February 2023Planning permission granted
13 February 2023Appeal allowed
13 February 2026Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
13 December 2022
Operator or applicant
Low Carbon UK Solar Investment Company Limited
Planning authority
Dorset
Planning application reference
P/FUL/2021/02046
Appeal reference
APP/D1265/W/22/3300299
Site area
39.1 ha
Address (REPD)
Park Farm Access To Park Farm Gillingham
Council area (by location)
Dorset
Time to decision
84 weeks
Contracts for Difference
AR5
Name in REPD
Fernbrook - Solar farm & Battery storage
REPD reference
8505

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hawkers Hill Energy Parkbattery storage20operational3.4
Shaftesbury Energy Parkbattery storage100approved, not built3.4
Motcombe Road, Motcombe Solar Pv Arrayssolar farm12application submitted4.1
Land east of Littledown Business Parksolar farm6.2operational4.8
Stour Row Solar Farmsolar farm12permission expired5.0
Manor Farm (Dorset)solar farm5operational5.3
Higher Farmsolar farm11refused on appeal5.4
Silton Wind Farmwind farm10refused on appeal5.7
Clapton Farm Solar Parksolar farm5operational7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0281, -2.2549).