Higher Farm (11 MW solar farm)

Higher Farm is an 11 MW solar farm project in Dorset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 23 July 2020; the record was last updated on 25 September 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11 MWsolar farm
refused on appealstatus in REPD
25 September 2020record last updated
Dorsetcouncil area

Planning timeline

DateStage
1 April 2019Application submitted
26 November 2019Appeal lodged
23 July 2020Appeal refused

Project details

Technology
solar farm
Capacity
11 MW
Status (REPD)
refused on appeal
Record last updated
25 September 2020
Operator or applicant
NextPower Higher Farm Limited
Planning authority
Dorset
Planning application reference
2/2019/0470/FUL
Appeal reference
3241953
Site area
21.4 ha
Address (REPD)
Land At E 378449 N 121922, Fifehead Magdalen, Higher Farm Fifehead, Gillingham, Dorset
Council area (by location)
Dorset
REPD reference
6569

Who decides

ApplicationsDorsetUK
Decided applications (solar, wind, battery)12510,236
Refused23 (18%)19%
Solar refused15 of 10512%
Onshore wind refused5 of 545%
Battery storage refused3 of 1516%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed6 / 6—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stour Row Solar Farmsolar farm12permission expired4.3
Fernbrook Solar farm & Battery storagesolar farm49.9approved, not built5.4
Land at Stalbridge Parksolar farm5operational5.5
Manor Farm (Dorset)solar farm5operational6.6
Land at Sutor Farmsolar farm5operational7.2
Shaftesbury Energy Parkbattery storage100approved, not built7.2
Hawkers Hill Energy Parkbattery storage20operational7.2
Clapton Farm Solar Parksolar farm5operational7.3
Silton Wind Farmwind farm10refused on appeal7.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9953, -2.3114).