Energy Projects Near You

Solar, wind and battery projects near Templecombe (BA8)

14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BA8 (Somerset): 2 approved but not yet running, 10 operational. The largest live scheme is Brains Solar Farm (18.8 MW solar farm, approved on 10 January 2022, not yet built; REPD status may be out of date), 5.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects within 10 km
0awaiting a decision
2approved, not running
10operational

Projects within 10 km of BA8

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land at Bowden Lanesolar farmsolar farm5operationalupdated Jun 2017Jun 2015granted Oct 2015Jun 2017Somerset2.0
Land at Stalbridge Parksolar farmsolar farm5operationalupdated Jun 2017Jul 2015granted Oct 2015Jun 2017Dorset3.4
Milborne Port Solar Farmsolar farmsolar farm4.2operationalupdated Jun 2018May 2015granted Aug 2016Jun 2018Somerset3.8
Land at Sutor Farmsolar farmsolar farm5operationalupdated Jun 2016Oct 2014granted Mar 2015Jun 2016Somerset4.6
Brains Solar Farmsolar farmsolar farm18.8approved, not built may be out of dateupdated Jan 2022Jul 2021granted Jan 2022Jan 2022Somerset5.1
Higher Hatherleigh Solar Farm extensionsolar farmsolar farm1.5operationalupdated Jul 2013Oct 2012granted Feb 2013Jul 2013Somerset5.3
Higher Hatherleigh Solar Farmsolar farmsolar farm3.5operationalupdated Jul 2013Mar 2012granted Aug 2012Jul 2013Somerset5.4
Hook Valley Solar Parksolar farmsolar farm17operationalupdated Aug 2014Nov 2012granted Sep 2013Aug 2014Somerset6.0
Higher Farmsolar farmsolar farm11refused on appealupdated Sep 2020Apr 2019—Sep 2020Dorset7.0
Symphony Farmwind farmwind farm3.9refusedupdated Oct 2013Oct 2003refused Mar 2004Oct 2013Somerset7.7
Clapton Farm Solar Parksolar farmsolar farm5operationalupdated Jun 2017Jul 2015granted Nov 2015Jun 2017Somerset8.1
Slaughtergate Farmsolar farmsolar farm1.8operationalupdated Apr 2013Aug 2012granted Nov 2012Apr 2013Dorset8.9
Manor Farm (Dorset)solar farmsolar farm5operationalupdated Jul 2014Aug 2013granted Nov 2013Jul 2014Dorset9.2
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Brains Solar Farmbattery storagebattery storage—approved, not built may be out of dateupdated Jan 2022Jul 2021granted Jan 2022Jan 2022Somerset5.1

Distance from the average position of the BA8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm120110118.8
Wind farm100010
Battery storage101000

MW in pipeline: pending, approved and under-construction capacity.

How Somerset decides solar, wind and battery applications

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

All projects in Somerset

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BA8, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.