Land at Bowden Lane (5 MW solar farm)

Land at Bowden Lane is a 5 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 23 June 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
23 June 2017record last updated
Somersetcouncil area

Planning timeline

DateStage
16 June 2015Application submitted
19 October 2015Planning permission granted
4 January 2017Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
23 June 2017
Operator or applicant
British Solar Renewables / NextEnergy Solar Fund (NESF)
Planning authority
Somerset
Planning application reference
15/02718/FUL
Site area
9.0 ha
Address (REPD)
Land at Bowden Lane, Henstridge, Templecombe
Council area (by location)
Somerset
Time to decision
18 weeks
REPD reference
5428

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Stalbridge Parksolar farm5operational3.5
Land at Sutor Farmsolar farm5operational6.5
Brains Solar Farmsolar farm18.8approved, not built6.9
Hook Valley Solar Parksolar farm17operational7.4
Higher Farmsolar farm11refused on appeal8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9818, -2.4287).