Energy Projects Near You

Brains Solar Farm (18.8 MW)

Brains Solar Farm is an 18.8 MW solar farm project in Somerset, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 10 January 2022, not yet built; the record was last updated on 19 January 2022. REPD also records that the planning permission expired on 10 January 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18.8 MWsolar farm
approved, not builtmay be out of datestatus in REPD
19 January 2022record last updated
Somersetcouncil area

REPD also records that the planning permission expired on 10 January 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
22 July 2021Application submitted
10 January 2022Planning permission granted
10 January 2025Permission expired

Project details

Technology
solar farm
Capacity
18.8 MW
Status (REPD)
approved, not built
Record last updated
19 January 2022
Operator or applicant
NextPower SPV 13 Limited
Planning authority
Somerset
Planning application reference
21/02205/FUL
Site area
29.6 ha
Address (REPD)
Solar Site South Of Brains Farm Moor Lane Wincanton
Council area (by location)
Somerset
Time to decision
25 weeks
REPD reference
9370

Recorded together with Hazelrigg Lane, Scotforth Solar Farm (16.5 MW solar farm, under construction).

Who decides

ApplicationsSomersetUK
Decided applications (solar, wind, battery)18510,236
Refused46 (25%)19%
Solar refused34 of 15312%
Onshore wind refused9 of 1045%
Battery storage refused3 of 2216%
Median time from submission to decision14.0 weeks17.0 weeks
Appeals lodged / allowed17 / 9—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Sutor Farmsolar farm5operational0.9
Hook Valley Solar Parksolar farm17operational2.6
Clapton Farm Solar Parksolar farm5operational4.0
Manor Farm (Dorset)solar farm5operational5.9
Silton Wind Farmwind farm10refused on appeal6.8
Land at Bowden Lanesolar farm5operational6.9
Land at Stalbridge Parksolar farm5operational7.8
Higher Farmsolar farm11refused on appeal8.0
Sheephouse Farm solar parksolar farm9refused8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0416, -2.3996).