Hazelrigg Lane, Scotforth Solar Farm (16.5 MW)

Hazelrigg Lane, Scotforth Solar Farm is a 16.5 MW solar farm project in Lancaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction; the record was last updated on 23 April 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.5 MWsolar farm
under constructionstatus in REPD
23 April 2025record last updated
Lancastercouncil area

Planning timeline

DateStage
7 October 2021Application submitted
9 March 2022Planning permission granted

Project details

Technology
solar farm
Capacity
16.5 MW
Status (REPD)
under construction
Record last updated
23 April 2025
Operator or applicant
BeBa Energy UK Limited / University of Lancaster
Planning authority
Lancaster
Planning application reference
21/01247/FUL
Site area
21.4 ha
Address (REPD)
Hazelrigg Lane Scotforth, Lancaster
Council area (by location)
Lancaster
Time to decision
22 weeks
Name in REPD
Hazelrigg Lane, Scotforth - Solar Farm
REPD reference
9372

Who decides

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Arna Wood Solarsolar farm6.2operational1.9
Moorside Farm Solar Farmsolar farm28approved, not built3.6
Hillside Farm, Lancaster Roadbattery storage100approved, not built3.9
Bay Gatewaybattery storage200approved, not built4.4
Caton Road, Lancasterbattery storage25approved, not built4.5
Heysham South Wind Farmwind farm7.5operational4.6
Heysham Energy Storage Projectbattery storage200approved, not built6.0
Fanny House Farm, Bay Gatewaybattery storage940approved, not built6.0
Fanny House Farmsolar farm5operational6.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0278, -2.7957).