Energy Projects Near You

Solar, wind and battery projects near Lancaster (LA2)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LA2 (Lancaster): 5 approved but not yet running, 2 operational. The largest live scheme is Moorside Farm Solar Farm (28 MW solar farm, approved on 14 November 2022, not yet built; REPD status may be out of date), 7.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
5approved, not running
2operational

Projects within 10 km of LA2

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Caton Moor Windfarm Repoweringwind farmwind farm16operationalupdated May 2009Nov 2002granted Oct 2004May 2009Lancaster1.2
Claughton Moorwind farmwind farm23refusedupdated Jul 2013Feb 2013refused Jun 2013Jul 2013Lancaster2.1
Moorside Farm Solar Farmsolar farmsolar farm28approved, not built may be out of dateupdated Sep 2024Jan 2022granted Nov 2022Sep 2024Lancaster7.0
Caton Road, Lancasterbattery storagebattery storage25approved, not builtupdated Dec 2022Nov 2021granted Dec 2022Dec 2022Lancaster7.6
Hazelrigg Lane, Scotforth Solar Farmsolar farmsolar farm16.5under constructionupdated Apr 2025Oct 2021granted Mar 2022Apr 2025Lancaster9.2
Burrow Beck Solar farmsolar farmsolar farm4approved, not builtupdated Feb 2025Feb 2024granted Jan 2025Feb 2025Lancaster9.3
Lancaster University (wind)wind turbinewind turbine2operationalupdated Apr 2013Oct 2010granted Aug 2011Apr 2013Lancaster9.7
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Brades Farm, Farleton Old Road, Farletonrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022Jun 2022granted Jul 2022Jun 2022Lancaster3.7

Distance from the average position of the LA2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm3030048.5
Rooftop solar101000.3
Wind farm200110
Wind turbine100100
Battery storage1010025

MW in pipeline: pending, approved and under-construction capacity.

How Lancaster decides solar, wind and battery applications

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

All projects in Lancaster

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near LA2, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.