Energy Projects Near You

Renewable energy projects in Lancaster

27 solar, wind or battery projects of 150 kW or more are located in Lancaster (REPD, July 2026 extract): 0 pending, 17 approved but not running, 7 operational and 1 refused. The council refused 5 of 30 decided applications (17%; UK 19%), with a median 28 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27projects in the council area
0awaiting a decision
17approved, not running
17%of decisions refused

How Lancaster decides

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Projects in Lancaster

Projects of 1 MW and more (22)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Fanny House Farm, Bay Gatewaybattery storagebattery storage940approved, not builtupdated Dec 2023Jun 2023granted Nov 2023Dec 2023
Heysham Energy Storage Projectbattery storagebattery storage200approved, not built may be out of dateupdated Jul 2025Aug 2021granted May 2022Jul 2025
Bay Gatewaybattery storagebattery storage200approved, not builtupdated May 2025Aug 2024granted Mar 2025May 2025
Hillside Farm, Lancaster Roadbattery storagebattery storage100approved, not builtupdated Sep 2023Dec 2022granted Sep 2023Sep 2023
North Side Bay Gateway, Heyshambattery storagebattery storage90approved, not builtupdated Aug 2025Feb 2025granted Jul 2025Aug 2025
Lancaster Power Extension, Middleton Road Energy Storage Facilitybattery storagebattery storage50approved, not built may be out of dateupdated Mar 2025Sep 2022granted May 2023Mar 2025
Middleton Clean Energy Plantbattery storagebattery storage49.9approved, not built may be out of dateupdated Sep 2022Oct 2018granted Jan 2020Sep 2022
Moorside Farm Solar Farmsolar farmsolar farm28approved, not built may be out of dateupdated Sep 2024Jan 2022granted Nov 2022Sep 2024
Caton Road, Lancasterbattery storagebattery storage25approved, not builtupdated Dec 2022Nov 2021granted Dec 2022Dec 2022
Claughton Moorwind farmwind farm23refusedupdated Jul 2013Feb 2013refused Jun 2013Jul 2013
Hazelrigg Lane, Scotforth Solar Farmsolar farmsolar farm16.5under constructionupdated Apr 2025Oct 2021granted Mar 2022Apr 2025
Caton Moor Windfarm Repoweringwind farmwind farm16operationalupdated May 2009Nov 2002granted Oct 2004May 2009
Port Of Heysham Wind Farmwind farmwind farm9application withdrawnupdated Jan 2014Sep 2011—Jan 2014
Heysham South Wind Farmwind farmwind farm7.5operationalupdated May 2015Jul 2011granted Nov 2012May 2015
Arna Wood Solarsolar farmsolar farm6.2operationalupdated Jul 2017Aug 2014granted Jul 2015Jul 2017
Fanny House Farmsolar farmsolar farm5operationalupdated Dec 2015Mar 2015granted Jun 2015Dec 2015
Land North of Saddler Nook Lanesolar farmsolar farm5permission expiredupdated Aug 2019Aug 2015granted Oct 2015Aug 2019
Burrow Beck Solar farmsolar farmsolar farm4approved, not builtupdated Feb 2025Feb 2024granted Jan 2025Feb 2025
Salt Ayre Leisure Centre Solar Farmsolar farmsolar farm3approved, not built may be out of dateupdated Feb 2022Jan 2021granted Apr 2021Feb 2022
Lancaster University (wind)wind turbinewind turbine2operationalupdated Apr 2013Oct 2010granted Aug 2011Apr 2013
Fanny House Farm/Heysham Mosswind turbinewind turbine1.5operationalupdated Feb 2016Jan 2011granted Oct 2012Feb 2016
Lancaster Wastewater Treatment Workssolar farmsolar farm1.2operationalupdated Nov 2018Aug 2016granted Jan 2017Nov 2018
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Southgate White, Lund Industrial Estaterooftop solarrooftop solar0.8approved, not builtupdated Mar 2025Feb 2025granted Mar 2025Mar 2025
Border Force Warehouse, South Quayrooftop solarrooftop solar0.5approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025
Peterson UK, North Quayrooftop solarrooftop solar0.5approved, not builtupdated Apr 2025Feb 2025granted Mar 2025Apr 2025
Brades Farm, Farleton Old Road, Farletonrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022Jun 2022granted Jul 2022Jun 2022
Higher Crookhey Farm, Garstang Road Solar Panel Systemsolar farmsolar farm0.1approved, not built may be out of dateupdated Mar 2023Oct 2022granted Mar 2023Mar 2023

Postcode districts in Lancaster

DistrictProjects within 10 kmPendingApprovedOperational
LA1230157
LA28052
LA3220156
LA4220156
LA54030

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Lancaster by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.