Energy Projects Near You

Bay Gateway (200 MW battery storage)

Bay Gateway is a 200 MW battery storage project in Lancaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 March 2025, not yet built; the record was last updated on 6 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
6 May 2025record last updated
Lancastercouncil area

Planning timeline

DateStage
22 August 2024Application submitted
21 March 2025Planning permission granted
21 March 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
6 May 2025
Operator or applicant
Energi Generation
Planning authority
Lancaster
Planning application reference
24/00874/FUL
Address (REPD)
North Of A683 Bay Gateway Heaton With Oxcliffe
Council area (by location)
Lancaster
Time to decision
30 weeks
Name in REPD
Bay Gateway - Battery Storage Facility
REPD reference
17028

Earlier applications for this site

ApplicationMWSubmittedOutcome
Bay Gateway 21/00695/FUL99.930 June 2021replaced by a revised application

Who decides

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hillside Farm, Lancaster Roadbattery storage100approved, not built0.6
Heysham South Wind Farmwind farm7.5operational1.1
Fanny House Farm, Bay Gatewaybattery storage940approved, not built1.6
Fanny House Farmsolar farm5operational1.6
Heysham Energy Storage Projectbattery storage200approved, not built2.0
Middleton Clean Energy Plantbattery storage49.9approved, not built2.4
Lancaster Power Extension, Middleton Road Energy Storage Facilitybattery storage50approved, not built2.9
North Side Bay Gateway, Heyshambattery storage90approved, not built3.3
Arna Wood Solarsolar farm6.2operational3.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0432, -2.8583).