Energy Projects Near You

Fanny House Farm (5 MW solar farm)

Fanny House Farm is a 5 MW solar farm project in Lancaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 21 December 2015; the record was last updated on 22 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
22 December 2015record last updated
Lancastercouncil area

Planning timeline

DateStage
4 March 2015Application submitted
30 June 2015Planning permission granted
1 November 2015Construction started
21 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
22 December 2015
Operator or applicant
Primrose Solar
Planning authority
Lancaster
Planning application reference
15/00243/FUL
Address (REPD)
Fanny House Farm, Heysham
Council area (by location)
Lancaster
Time to decision
17 weeks
REPD reference
5099

Who decides

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fanny House Farm, Bay Gatewaybattery storage940approved, not built<0.1
Bay Gatewaybattery storage200approved, not built1.6
Middleton Clean Energy Plantbattery storage49.9approved, not built1.7
Heysham Energy Storage Projectbattery storage200approved, not built1.9
Heysham South Wind Farmwind farm7.5operational2.2
Hillside Farm, Lancaster Roadbattery storage100approved, not built2.3
North Side Bay Gateway, Heyshambattery storage90approved, not built2.5
Lancaster Power Extension, Middleton Road Energy Storage Facilitybattery storage50approved, not built3.0
Port Of Heysham Wind Farmwind farm9application withdrawn3.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0521, -2.8783).