Heysham South Wind Farm (7.5 MW)

Heysham South Wind Farm is a 7.5 MW wind farm project in Lancaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 24 April 2015; the record was last updated on 5 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
5 May 2015record last updated
Lancastercouncil area

Planning timeline

DateStage
28 July 2011Application submitted
28 November 2012Planning permission granted
4 August 2014Construction started
24 April 2015Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
5 May 2015
Operator or applicant
Banks Renewables
Planning authority
Lancaster
Planning application reference
11/00689/FUL
Turbines
3
Address (REPD)
Lancaster Morecambe Bypass, Heaton With Oxcliffe, Lancashire
Council area (by location)
Lancaster
Time to decision
70 weeks
REPD reference
4174

Who decides

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hillside Farm, Lancaster Roadbattery storage100approved, not built1.0
Bay Gatewaybattery storage200approved, not built1.1
Heysham Energy Storage Projectbattery storage200approved, not built1.4
Lancaster Power Extension, Middleton Road Energy Storage Facilitybattery storage50approved, not built2.0
Middleton Clean Energy Plantbattery storage49.9approved, not built2.1
Fanny House Farm, Bay Gatewaybattery storage940approved, not built2.1
Fanny House Farmsolar farm5operational2.2
Arna Wood Solarsolar farm6.2operational3.1
Port Of Heysham Wind Farmwind farm9application withdrawn3.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0342, -2.865).