Energy Projects Near You

Heysham Energy Storage Project (200 MW)

Heysham Energy Storage Project is a 200 MW battery storage project in Lancaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 May 2022, not yet built; the record was last updated on 15 July 2025. REPD also records that the planning permission expired on 26 May 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtmay be out of datestatus in REPD
15 July 2025record last updated
Lancastercouncil area

REPD also records that the planning permission expired on 26 May 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
17 August 2021Application submitted
23 May 2022Planning permission granted
26 May 2025Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
15 July 2025
Operator or applicant
Kona Energy Limited
Planning authority
Lancaster
Planning application reference
21/01069/FUL
Address (REPD)
N/O A683 Lancaster, Morecambe Bypass, Morecambe
Council area (by location)
Lancaster
Time to decision
40 weeks
REPD reference
9545

Who decides

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Middleton Clean Energy Plantbattery storage49.9approved, not built0.8
Lancaster Power Extension, Middleton Road Energy Storage Facilitybattery storage50approved, not built1.2
Heysham South Wind Farmwind farm7.5operational1.4
Fanny House Farm, Bay Gatewaybattery storage940approved, not built1.8
Fanny House Farmsolar farm5operational1.9
Bay Gatewaybattery storage200approved, not built2.0
Port Of Heysham Wind Farmwind farm9application withdrawn2.2
Hillside Farm, Lancaster Roadbattery storage100approved, not built2.2
North Side Bay Gateway, Heyshambattery storage90approved, not built4.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.036, -2.886).