Arna Wood Solar (6.2 MW)

Arna Wood Solar is a 6.2 MW solar farm project in Lancaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 28 July 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.2 MWsolar farm
operationalstatus in REPD
28 July 2017record last updated
Lancastercouncil area

Planning timeline

DateStage
18 August 2014Application submitted
1 July 2015Planning permission granted
31 January 2017Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
6.2 MW
Status (REPD)
operational
Record last updated
28 July 2017
Operator or applicant
BE Renewables (on behalf of Arna Wood)
Planning authority
Lancaster
Planning application reference
14/00907/FUL
Site area
12.7 ha
Address (REPD)
Arna Wood Farm, East Arna Wood Lane, Lancaster, Lancashire
Council area (by location)
Lancaster
Time to decision
45 weeks
REPD reference
2263

Who decides

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hazelrigg Lane, Scotforth Solar Farmsolar farm16.5under construction1.9
Hillside Farm, Lancaster Roadbattery storage100approved, not built2.6
Heysham South Wind Farmwind farm7.5operational3.1
Bay Gatewaybattery storage200approved, not built3.3
Heysham Energy Storage Projectbattery storage200approved, not built4.4
Lancaster Power Extension, Middleton Road Energy Storage Facilitybattery storage50approved, not built4.6
Fanny House Farm, Bay Gatewaybattery storage940approved, not built4.9
Fanny House Farmsolar farm5operational4.9
Moorside Farm Solar Farmsolar farm28approved, not built5.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0223, -2.8228).