Energy Projects Near You

Land North of Saddler Nook Lane (5 MW solar farm)

Land North of Saddler Nook Lane is a 5 MW solar farm project in Lancaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 22 October 2018; the record was last updated on 13 August 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
permission expiredstatus in REPD
13 August 2019record last updated
Lancastercouncil area

Planning timeline

DateStage
10 August 2015Application submitted
22 October 2015Planning permission granted
22 October 2018Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
permission expired
Record last updated
13 August 2019
Operator or applicant
Delta Solar
Planning authority
Lancaster
Planning application reference
15/00876/FUL
Site area
11.9 ha
Address (REPD)
Land North Of, Saddler Nook Lane, Whittington, Carnforth
Council area (by location)
Lancaster
Time to decision
10 weeks
REPD reference
5509

Who decides

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cinderbarrow Lanesolar farm5abandoned7.3
Ravens Closesolar farm5operational8.1
Fountain Lot Solar Farmsolar farm5refused9.8
Armistead Wind Farmwind farm12operational9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1878, -2.6285).