Energy Projects Near You

Ravens Close (5 MW solar farm)

Ravens Close is a 5 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 14 March 2017; the record was last updated on 2 March 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
2 March 2018record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
2 February 2015Application submitted
10 June 2015Refused by the planning authority
30 July 2015Appeal lodged
21 March 2016Planning permission granted
21 March 2016Appeal allowed
24 October 2016Construction started
14 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
2 March 2018
Operator or applicant
NESF (formerly Tau Solar)
Planning authority
North Yorkshire
Planning application reference
08/2015/15473
Appeal reference
APP/C2708/W/15/3129664
Site area
6.7 ha
Address (REPD)
Solar PV Farm Grazing Land, Ravens Close, Lower Bentham, Lancaster,
Council area (by location)
North Yorkshire
Time to decision
59 weeks
REPD reference
5017

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Fountain Lot Solar Farmsolar farm5refused2.9
Land North of Saddler Nook Lanesolar farm5permission expired8.1
Claughton Moorwind farm23refused8.9
Caton Moor Windfarm Repoweringwind farm16operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1308, -2.552).