Caton Moor Windfarm Repowering (16 MW)

Caton Moor Windfarm Repowering is a 16 MW wind farm project in Lancaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 June 2006; the record was last updated on 6 May 2009.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWwind farm
operationalstatus in REPD
6 May 2009record last updated
Lancastercouncil area

Planning timeline

DateStage
7 November 2002Application submitted
10 September 2003Refused by the planning authority
1 October 2004Planning permission granted
1 October 2004Appeal allowed
1 May 2006Construction started
1 June 2006Operational

Project details

Technology
wind farm
Capacity
16 MW
Status (REPD)
operational
Record last updated
6 May 2009
Operator or applicant
Hainsford Energy
Planning authority
Lancaster
Planning application reference
21331
Appeal reference
02/01331/FUL
Turbines
8
Address (REPD)
Littledale, Caton Lancashire
Council area (by location)
Lancaster
Time to decision
99 weeks
REPD reference
3171

Who decides

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Claughton Moorwind farm23refused1.0
Moorside Farm Solar Farmsolar farm28approved, not built8.2
Caton Road, Lancasterbattery storage25approved, not built8.7
Ravens Closesolar farm5operational9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0698, -2.654).