Energy Projects Near You

Caton Road, Lancaster (25 MW battery storage)

Caton Road, Lancaster is a 25 MW battery storage project in Lancaster, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 7 December 2022, not yet built; the record was last updated on 13 December 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25 MWbattery storage
approved, not builtstatus in REPD
13 December 2022record last updated
Lancastercouncil area

Planning timeline

DateStage
19 November 2021Application submitted
7 December 2022Planning permission granted
7 December 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
25 MW
Status (REPD)
approved, not built
Record last updated
13 December 2022
Operator or applicant
Energi Generation 12 Limited
Planning authority
Lancaster
Planning application reference
21/01351/FUL
Address (REPD)
The North East Of Kidds Transport Limited Caton Road Lancaster
Council area (by location)
Lancaster
Time to decision
55 weeks
Name in REPD
Caton Road, Lancaster - Battery Storage Facility
REPD reference
10047

Who decides

ApplicationsLancasterUK
Decided applications (solar, wind, battery)3010,236
Refused5 (17%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 745%
Battery storage refused0 of 916%
Median time from submission to decision28.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Moorside Farm Solar Farmsolar farm28approved, not built1.3
Hazelrigg Lane, Scotforth Solar Farmsolar farm16.5under construction4.5
North Side Bay Gateway, Heyshambattery storage90approved, not built5.0
Hillside Farm, Lancaster Roadbattery storage100approved, not built5.4
Bay Gatewaybattery storage200approved, not built5.4
Arna Wood Solarsolar farm6.2operational5.6
Fanny House Farm, Bay Gatewaybattery storage940approved, not built6.2
Fanny House Farmsolar farm5operational6.2
Heysham South Wind Farmwind farm7.5operational6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.0683, -2.7869).