Renewable energy projects in North Yorkshire
211 solar, wind or battery projects of 150 kW or more are located in North Yorkshire (REPD, July 2026 extract): 35 pending, 124 approved but not running, 27 operational and 10 refused. The council refused 28 of 165 decided applications (17%; UK 19%), with a median 15 weeks from submission to decision.
211projects in the council area
35awaiting a decision
124approved, not running
17%of decisions refused
How North Yorkshire decides
| Applications | North Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 165 | 10,236 |
| Refused | 28 (17%) | 19% |
| Solar refused | 15 of 112 | 12% |
| Onshore wind refused | 8 of 24 | 45% |
| Battery storage refused | 5 of 29 | 16% |
| Median time from submission to decision | 15.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 13 / 12 | — |
Projects in North Yorkshire
Projects of 1 MW and more (100)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Mowbray Battery Energy Storage Stationbattery storage | battery storage | 1,000 | application submittedupdated Feb 2025 | Dec 2024 | — | Feb 2025 |
| Eggborough Battery Energy Storage Systembattery storage | battery storage | 550 | approved, not builtupdated Jul 2025 | Jun 2024 | granted May 2025 | Jul 2025 |
| Eggborough Power Station, Selby Roadbattery storage | battery storage | 500 | approved, not built may be out of dateupdated Sep 2025 | Oct 2022 | granted Jan 2023 | Sep 2025 |
| Solar Farm at Light Valley Solar Sitessolar farm | solar farm | 500 | application submittedupdated Jun 2026 | Mar 2026 | — | Jun 2026 |
| Monk Fryston Battery Storagebattery storage | battery storage | 320 | under constructionupdated Oct 2025 | Jun 2021 | granted Dec 2022 | Oct 2025 |
| Springfield Farm, Hensallbattery storage | battery storage | 240 | approved, not builtupdated Jul 2024 | Mar 2023 | granted May 2024 | Jul 2024 |
| Springfield Farm, Weeland Roadbattery storage | battery storage | 240 | approved, not builtupdated Jun 2025 | Jun 2024 | granted May 2025 | Jun 2025 |
| Kellingley Farm, Stocking Lanebattery storage | battery storage | 240 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 |
| Drax Re-Powerbattery storage | battery storage | 200 | approved, not builtupdated Jan 2020 | Feb 2018 | granted May 2018 | Jan 2020 |
| Stocking Lane Battery Energy Facilitybattery storage | battery storage | 200 | application submitted may be out of dateupdated Oct 2023 | Sep 2023 | — | Oct 2023 |
| Corner Of Weeland Road, Lunn Lanebattery storage | battery storage | 200 | approved, not builtupdated Sep 2025 | Nov 2023 | granted Jul 2025 | Sep 2025 |
| Rawfield Lanebattery storage | battery storage | 200 | approved, not builtupdated Sep 2025 | Oct 2024 | granted Aug 2025 | Sep 2025 |
| Low Moor Lane, Scottonbattery storage | battery storage | 200 | application submittedupdated Mar 2026 | Dec 2025 | — | Mar 2026 |
| Helios Renewable Energy Projectsolar farm | solar farm | 190 | approved, not builtupdated Dec 2025 | Jul 2024 | granted Dec 2025 | Dec 2025 |
| Hales Lanebattery storage | battery storage | 100 | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted May 2022 | May 2022 |
| Third Energy UK Gas Limitedbattery storage | battery storage | 100 | approved, not built may be out of dateupdated Mar 2023 | Aug 2021 | granted Oct 2021 | Mar 2023 |
| Lakeside Energy Storage Facilitybattery storage | battery storage | 99.9 | approved, not built may be out of dateupdated Dec 2021 | Dec 2020 | granted May 2021 | Dec 2021 |
| Station Road, Carltonbattery storage | battery storage | 99 | approved, not builtupdated Jun 2025 | Oct 2024 | granted May 2025 | Jun 2025 |
| Barlow Road, Barlow Roadbattery storage | battery storage | 80 | application withdrawnupdated Mar 2025 | Aug 2023 | — | Mar 2025 |
| Monk Fryston Battery Storagebattery storage | battery storage | 57 | under constructionupdated Oct 2025 | May 2021 | granted Aug 2022 | Oct 2025 |
| Darlington Road, Skeebysolar farm | solar farm | 55 | operationalupdated Nov 2024 | Oct 2021 | granted Nov 2022 | Nov 2024 |
| New Oaks, Station Roadbattery storage | battery storage | 50 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 |
| Carlton Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated Feb 2026 | Feb 2023 | granted Apr 2024 | Feb 2026 |
| Pilmoor Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated May 2026 | Nov 2023 | granted Sep 2024 | May 2026 |
| Cayton Solar farmsolar farm | solar farm | 49.9 | approved, not builtupdated Aug 2023 | Jun 2019 | granted Jan 2022 | Aug 2023 |
| South Lowfields Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Aug 2020 | Sep 2019 | granted Dec 2019 | Aug 2020 |
| Camblesforth Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Feb 2021 | Jun 2021 | granted Jul 2022 | Feb 2021 |
| Osgodby Grange, Osgodby Solar Energysolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Mar 2026 | Sep 2021 | granted Jul 2022 | Mar 2026 |
| Os Field 6800 Fence Dike Lane Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Jun 2023 | May 2021 | granted Jun 2023 | Jun 2023 |
| Hillam Grange, Austfield Lane Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Jan 2026 | Dec 2023 | granted Dec 2025 | Jan 2026 |
| Os Field, Husthwaitesolar farm | solar farm | 49.9 | approved, not builtupdated Nov 2025 | Sep 2023 | granted Oct 2025 | Nov 2025 |
| Scalm Park, Wistow Solar Farm & Battery Energy Storagesolar farm | solar farm | 49.9 | approved, not builtupdated Sep 2025 | Nov 2024 | granted Sep 2025 | Sep 2025 |
| Broad Lane, Cawood Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 |
| Overton Grange, Overton Road Solar Farm Battery Energy Storagesolar farm | solar farm | 49.9 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 |
| Newlands Farm, Turnham Lanesolar farm | solar farm | 49.9 | application submittedupdated Nov 2025 | Jul 2025 | — | Nov 2025 |
| Leys Lanesolar farm | solar farm | 49.9 | application submittedupdated Oct 2025 | Jun 2025 | — | Oct 2025 |
| Green Lane, Moor Monkton Solar Panels & Battery Energy Storage Systemsolar farm | solar farm | 49.9 | application submittedupdated Aug 2025 | Apr 2025 | — | Aug 2025 |
| Wormald Green Solar Farmsolar farm | solar farm | 43 | approved, not builtupdated Mar 2026 | Dec 2023 | granted Jul 2025 | Mar 2026 |
| Rusholme Grangebattery storage | battery storage | 40 | operationalupdated Aug 2024 | May 2021 | granted Sep 2021 | Aug 2024 |
| Hull Road, Lundbattery storage | battery storage | 40 | approved, not builtupdated Jan 2025 | Jul 2024 | granted Jan 2025 | Jan 2025 |
| Solar Farm at North Of Brompton On Swalesolar farm | solar farm | 39.3 | approved, not builtupdated Sep 2025 | Feb 2025 | granted Aug 2025 | Sep 2025 |
| Darlington Road, Skeebybattery storage | battery storage | 35 | under constructionupdated Mar 2026 | Jun 2023 | granted Aug 2023 | Mar 2026 |
| York Solar Farmsolar farm | solar farm | 34.7 | operationalupdated May 2020 | Jun 2015 | granted Sep 2015 | May 2020 |
| Wormald Greenbattery storage | battery storage | 33 | operationalupdated Feb 2026 | Mar 2022 | granted Jun 2022 | Feb 2026 |
| Wood Lanewind farm | wind farm | 32.2 | application withdrawnupdated Jan 2016 | Jul 2009 | — | Jan 2016 |
| Eastgate House Farm, Seamer Solar Farmsolar farm | solar farm | 32 | under constructionupdated Apr 2024 | Aug 2021 | granted Oct 2022 | Apr 2024 |
| East Cowton Solar Farmsolar farm | solar farm | 30.8 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 |
| Windmill Farm Solar Farm (Old Malton)solar farm | solar farm | 30.4 | approved, not builtupdated Feb 2026 | Jan 2023 | refused Oct 2023 | Feb 2026 |
| Boscar Layby, Raskelfsolar farm | solar farm | 30 | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 |
| Stell Solar Farmsolar farm | solar farm | 30 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 |
| Northallertonsolar farm | solar farm | 28 | abandonedupdated Jun 2018 | Jun 2015 | granted Oct 2015 | Jun 2018 |
| Boscar Grange Farmbattery storage | battery storage | 27 | operationalupdated Dec 2019 | Oct 2018 | — | Dec 2019 |
| Redmoor Farmsolar farm | solar farm | 25.5 | permission expiredupdated Sep 2020 | Aug 2015 | granted Jan 2017 | Sep 2020 |
| East Heslerton Wind Farmwind farm | wind farm | 25 | refused on appealupdated Jul 2014 | Mar 2011 | refused May 2013 | Jul 2014 |
| Rusholme Wind Farmwind farm | wind farm | 24 | operationalupdated Dec 2014 | Jul 2004 | granted Oct 2006 | Dec 2014 |
| Carr House Farm, East Heslerton Solar Farmsolar farm | solar farm | 23.5 | approved, not builtupdated Jun 2025 | Mar 2024 | granted Jun 2025 | Jun 2025 |
| Solar Farm at East Appleton Farmsolar farm | solar farm | 23.5 | application submittedupdated Oct 2025 | Jun 2025 | — | Oct 2025 |
| Penny Pot Wind Farmwind farm | wind farm | 21 | application withdrawnupdated Mar 2014 | Jul 2012 | — | Mar 2014 |
| Solar Farm at N/O Black Bridge Danby Wiskesolar farm | solar farm | 19 | application submittedupdated Jul 2025 | May 2025 | — | Jul 2025 |
| Juniper Farm, Main Street Solar Farmsolar farm | solar farm | 18.8 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 |
| Solar Farm at Woodcock Solar Farmsolar farm | solar farm | 18.5 | refusedupdated May 2026 | Jan 2025 | refused Mar 2026 | May 2026 |
| Queen Margarets Industrial Estatebattery storage | battery storage | 18 | abandonedupdated Dec 2019 | Jul 2018 | — | Dec 2019 |
| Scalm Park / Bishopwoodwind farm | wind farm | 17.5 | appeal withdrawnupdated Aug 2018 | Jul 2009 | refused Jan 2013 | Aug 2018 |
| Knabs Ridge Windfarmwind farm | wind farm | 16 | operationalupdated May 2009 | Apr 2004 | granted Nov 2004 | May 2009 |
| Cleek Hallwind farm | wind farm | 15 | abandonedupdated Sep 2015 | Aug 2009 | granted Sep 2012 | Sep 2015 |
| Windmill Farm Solar Farm (Old Malton)battery storage | battery storage | 12.6 | approved, not builtupdated Feb 2026 | Jan 2023 | granted Feb 2025 | Feb 2026 |
| Station Lane, South Stainleysolar farm | solar farm | 10 | approved, not builtupdated May 2024 | Nov 2022 | granted Apr 2024 | May 2024 |
| Weeland Road, Kellingley Solar Farmsolar farm | solar farm | 10 | application submittedupdated Nov 2024 | Oct 2024 | — | Nov 2024 |
| Juniper Farm, Main Streetbattery storage | battery storage | 10 | application submittedupdated Aug 2025 | Jul 2025 | — | Aug 2025 |
| Broad Lane, Cawood Solar Farm & Battery Storagebattery storage | battery storage | 10 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 |
| Bullamoorwind farm | wind farm | 8 | permission expiredupdated Sep 2020 | Dec 2008 | granted Dec 2010 | Sep 2020 |
| High Boar Wind Farmwind farm | wind farm | 8 | refusedupdated Apr 2015 | Oct 2012 | refused Apr 2015 | Apr 2015 |
| Brightenber Hillwind farm | wind farm | 7.5 | refused on appealupdated Mar 2016 | Apr 2012 | refused Sep 2012 | Mar 2016 |
| Moto Wetherby Motorway Service Area, Deighton Gates Roundabout Solar Farmsolar farm | solar farm | 7 | approved, not builtupdated Aug 2024 | Nov 2023 | granted Aug 2024 | Aug 2024 |
| Seamer Windfarm - Stockton on Teeswind farm | wind farm | 6 | operationalupdated Nov 2012 | Mar 2009 | granted Aug 2009 | Nov 2012 |
| North East of Ainderby Steeplesolar farm | solar farm | 5.9 | operationalupdated Dec 2017 | Mar 2014 | granted Dec 2014 | Dec 2017 |
| Kingspan Insulation Solar Installationrooftop solar | rooftop solar | 5 | operationalupdated Jun 2017 | Dec 2013 | granted Mar 2014 | Jun 2017 |
| Barugh Farmsolar farm | solar farm | 5 | operationalupdated Jul 2017 | Nov 2014 | granted Jan 2015 | Jul 2017 |
| Cold Harbour Farmsolar farm | solar farm | 5 | operationalupdated Dec 2015 | Nov 2014 | granted Feb 2015 | Dec 2015 |
| Ravens Closesolar farm | solar farm | 5 | operationalupdated Mar 2018 | Feb 2015 | granted Mar 2016 | Mar 2018 |
| Land South of Highfield Housesolar farm | solar farm | 5 | operationalupdated Aug 2016 | Feb 2015 | granted Jun 2015 | Aug 2016 |
| Mill Hill Farmsolar farm | solar farm | 5 | operationalupdated Dec 2015 | Apr 2015 | granted Jul 2015 | Dec 2015 |
| Pollington Solar Farmsolar farm | solar farm | 5 | operationalupdated Oct 2017 | Apr 2015 | granted Jul 2015 | Oct 2017 |
| Land North of Sandhutton Lanesolar farm | solar farm | 5 | operationalupdated Dec 2017 | May 2015 | granted Sep 2015 | Dec 2017 |
| Land East of Appleton Farmsolar farm | solar farm | 5 | operationalupdated Jun 2018 | Jun 2015 | granted Sep 2015 | Jun 2018 |
| Land at Ash Row Farmsolar farm | solar farm | 5 | operationalupdated Feb 2016 | Jul 2015 | granted Sep 2015 | Feb 2016 |
| Land at Stripe Farmsolar farm | solar farm | 5 | operationalupdated Jun 2018 | Jun 2015 | granted Sep 2015 | Jun 2018 |
| Sudforth Lane (Kellingley Solar Farm)solar farm | solar farm | 5 | operationalupdated Oct 2017 | Apr 2015 | granted Aug 2015 | Oct 2017 |
| Fountain Lot Solar Farmsolar farm | solar farm | 5 | refusedupdated Dec 2015 | Oct 2015 | refused Jan 2016 | Dec 2015 |
| Sherburnrooftop solar | rooftop solar | 5 | operationalupdated Nov 2017 | Jan 2014 | — | Nov 2017 |
| Jenny Field Drivebattery storage | battery storage | 5 | approved, not built may be out of dateupdated Oct 2023 | Nov 2017 | granted Jan 2018 | Oct 2023 |
| Showfield Lanebattery storage | battery storage | 5 | approved, not built may be out of dateupdated Dec 2023 | Nov 2018 | granted Feb 2019 | Dec 2023 |
| Woodcock Solar Farm, Sweeming Lanebattery storage | battery storage | 4.7 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 |
| Escrick Park Community Power Projectwind farm | wind farm | 4.6 | application withdrawnupdated Jun 2011 | — | — | Jun 2011 |
| Chelker Reservoir Repowerwind farm | wind farm | 3.9 | application withdrawnupdated Dec 2011 | Feb 2011 | — | Dec 2011 |
| Ravens Closesolar farm | solar farm | 3.8 | refusedupdated Dec 2015 | Jul 2015 | refused Oct 2015 | Dec 2015 |
| Burton Top Farmsolar farm | solar farm | 3.6 | abandonedupdated Mar 2019 | Sep 2015 | granted Nov 2015 | Mar 2019 |
| Chelker Reservoir Repower (Resubmission)wind farm | wind farm | 1.7 | refusedupdated Mar 2012 | Oct 2011 | refused Mar 2012 | Mar 2012 |
| White Barn Farm, Station Roadwind farm | wind farm | 1.7 | application submitted | Apr 2026 | — | — |
| Dechra Pharmaceuticals Manufacturing, Building 3rooftop solar | rooftop solar | 1.6 | approved, not built may be out of dateupdated Jul 2022 | Jul 2022 | granted Sep 2022 | Jul 2022 |
Smaller schemes under 1 MW, mostly rooftop solar (60)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Whitby Seafoods, Stainsacre Lane Industrial Estaterooftop solar | rooftop solar | 0.9 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 |
| GXO Logistics, Hurricane Way Southrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jun 2025 | Mar 2025 | granted May 2025 | Jun 2025 |
| Cranswick Gourmet Pastry, Hugden Wayrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2022 | Oct 2022 | granted Dec 2022 | Dec 2022 |
| Haven Leisure, Primrose Avenuerooftop solar | rooftop solar | 0.7 | approved, not builtupdated May 2023 | Feb 2023 | granted Apr 2023 | May 2023 |
| Cranswick Country Foods, Seafox Courtrooftop solar | rooftop solar | 0.7 | under constructionupdated Apr 2023 | Oct 2022 | refused Dec 2022 | Apr 2023 |
| Halton East Quarriessolar farm | solar farm | 0.7 | approved, not builtupdated Mar 2026 | Nov 2025 | granted Feb 2026 | Mar 2026 |
| South Craven School, Holme Lane, Cross Hillsrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Oct 2024 | Nov 2024 |
| Well Lane, Sutton-On-The-Forest Solar Array &110KW Battery Storagesolar farm | solar farm | 0.6 | application submittedupdated May 2026 | Feb 2026 | — | May 2026 |
| AD Calvert Architectural, Stone Yard - Redevelopment Master Plansolar farm | solar farm | 0.5 | approved, not builtupdated Feb 2024 | Apr 2023 | granted Feb 2024 | Feb 2024 |
| J E Hartley, Roth Hill Lanerooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2025 | Feb 2025 | granted Apr 2025 | May 2025 |
| Rose Cottage, Easingwold To Craykerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Feb 2025 | Mar 2025 |
| Wildon grange, Mill Field Lanesolar farm | solar farm | 0.5 | approved, not built may be out of dateupdated Mar 2023 | Sep 2022 | granted Mar 2023 | Mar 2023 |
| J Revis & Sons, South Field Lanerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2023 | Jan 2023 | granted Mar 2023 | Mar 2023 |
| Marshall aerospace, Kirkbymoorsiderooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 |
| Ling Farm, Langtoftwind farm | wind farm | 0.5 | approved, not builtupdated Mar 2026 | Oct 2025 | granted Feb 2026 | Mar 2026 |
| William Hare, Eastfieldrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2025 | Feb 2025 | granted Apr 2025 | Apr 2025 |
| Scarborough Hospital, Woodlands Driverooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 |
| First Bus Hunslet Park Depot, Atkinson Streetrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Apr 2023 | Mar 2023 | granted Apr 2023 | Apr 2023 |
| Linton Mill, Main Streetrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 |
| Ripon Grammar School, Clotherholme Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2024 | Jun 2024 | granted Nov 2024 | Dec 2024 |
| Middleton Lodge, Kneeton Lanerooftop solar | rooftop solar | 0.4 | approved, not built may be out of dateupdated Mar 2023 | Dec 2022 | granted Feb 2023 | Mar 2023 |
| Friarage Hospitalrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Feb 2025 | Feb 2025 |
| Harrogate Convention Centrerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Oct 2021 | Aug 2021 | granted Oct 2021 | Oct 2021 |
| Darlington Roadrooftop solar | rooftop solar | 0.4 | application withdrawnupdated Nov 2022 | Sep 2022 | — | Nov 2022 |
| Yorkshire Water Plc Sewage Works - Ground Mounted Solar PV Developmentsolar farm | solar farm | 0.4 | approved, not builtupdated Feb 2021 | Jun 2023 | granted Jul 2023 | Feb 2021 |
| Deep Sea Electronics, Bridlingtonrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 |
| The Swinton Estate, Swinton Roadsolar farm | solar farm | 0.4 | approved, not builtupdated Dec 2025 | Jul 2025 | granted Nov 2025 | Dec 2025 |
| Harrogate South Waste Water Treatment Works - Ground Mounted Solar Arraysolar farm | solar farm | 0.4 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Jun 2023 | Aug 2023 |
| Hornington Manor, Oxton Lanerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Feb 2025 | Mar 2025 |
| Sainsburys Supermarket, Stainsacre Lanerooftop solar | rooftop solar | 0.3 | application submitted may be out of dateupdated Oct 2024 | Jul 2024 | — | Oct 2024 |
| Ripon Community Leisure Centre, Dallamires Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Jan 2026 | Mar 2026 |
| Lark Hall Farm, Romanby - Ground Mounted Solar Panelssolar farm | solar farm | 0.3 | approved, not built may be out of dateupdated Aug 2022 | Jul 2022 | granted Mar 2023 | Aug 2022 |
| Cardale Park - Ground Mounted Solar Panelssolar farm | solar farm | 0.3 | approved, not builtupdated Oct 2024 | Apr 2024 | granted Sep 2024 | Oct 2024 |
| Sainsburys Supermarket, Stainsacre Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2024 | Jul 2024 | granted Sep 2024 | Sep 2024 |
| Brickworks Forest Lane, Alnerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2024 | Oct 2024 | granted Dec 2024 | Dec 2024 |
| M.H.Poskitt, Weeland Roadsolar farm | solar farm | 0.3 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Nov 2025 | Jan 2026 |
| Barneby Way, Boroughbridgesolar farm | solar farm | 0.3 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Aug 2024 | Aug 2024 |
| Rabbit Hill Park, Allerton Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 |
| Leeming Bar Sewage Treatment, Blow Houses To Leeming Bridgesolar farm | solar farm | 0.3 | application submitted may be out of dateupdated Jul 2023 | Jul 2023 | — | Jul 2023 |
| Riverside Caravan Park, Slaidburn Road Solar PV Arraysrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2024 | Nov 2023 | granted Jan 2024 | Jan 2024 |
| Cayton Bay Holiday Park, Mill Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2024 | Apr 2024 | granted Jun 2024 | Jul 2024 |
| Babcock Land Defence Limited, Dsg Leyburn Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2024 | Jul 2024 | granted Sep 2024 | Dec 2024 |
| Hunmanby Grange, Cans Dale To The Grange Solar Panels & BESSrooftop solar | rooftop solar | 0.3 | application submitted | May 2026 | — | — |
| Duggleby Wold Farmhousewind turbine | wind turbine | 0.2 | approved, not builtupdated Jul 2022 | Jul 2022 | granted Nov 2022 | Jul 2022 |
| Pond View Farm, Tholthorpesolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated May 2023 | Feb 2022 | granted May 2023 | May 2023 |
| Park Farm, High Streetwind turbine | wind turbine | 0.2 | approved, not builtupdated Dec 2025 | Aug 2025 | granted Nov 2025 | Dec 2025 |
| Bartindale Road, Grindalewind turbine | wind turbine | 0.2 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 |
| Gara Farm, Weaverthorpewind turbine | wind turbine | 0.2 | approved, not builtupdated Jun 2026 | Nov 2025 | granted Apr 2026 | Jun 2026 |
| Selby War Memorial Hospital, Doncaster Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Jan 2026 | Apr 2026 |
| Reighton Sands Holiday Village, Sands Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated May 2023 | Feb 2023 | granted Apr 2023 | May 2023 |
| Heck Food, Lime Lanerooftop solar | rooftop solar | 0.2 | operationalupdated Jul 2024 | Oct 2023 | granted Dec 2023 | Jul 2024 |
| Forum Subsea Technologies, Ings Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2023 | Dec 2022 | granted Jan 2023 | Jan 2023 |
| Foss Way, Walkerville Industrial Estatesolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Mar 2023 | Dec 2022 | granted Jan 2023 | Mar 2023 |
| Filey Waste Water Treatment Works, Carr House Farmsolar farm | solar farm | 0.2 | approved, not builtupdated Oct 2023 | May 2023 | granted Oct 2023 | Oct 2023 |
| Malton Wastewater Treatment Works, Seven Lane Solar Panelssolar farm | solar farm | 0.2 | approved, not builtupdated Nov 2023 | Jun 2023 | granted Nov 2023 | Nov 2023 |
| Sawley Hall, Sawleysolar farm | solar farm | 0.2 | application withdrawnupdated Aug 2023 | Jun 2023 | — | Aug 2023 |
| Magdalen Grange Farm, Carr Lanewind turbine | wind turbine | 0.2 | approved, not builtupdated Apr 2026 | Oct 2025 | granted Mar 2026 | Apr 2026 |
| Cat Babbleton Farm, Gantonwind farm | wind farm | 0.2 | approved, not builtupdated Apr 2026 | May 2025 | granted Feb 2026 | Apr 2026 |
| Cross Thorns Farm, Pasture Roadwind turbine | wind turbine | 0.2 | approved, not builtupdated Jun 2026 | Nov 2025 | granted May 2026 | Jun 2026 |
| Long Green Farmsolar farm | solar farm | 0.2 | application submitted may be out of dateupdated Sep 2020 | Jun 2020 | — | Sep 2020 |
51 more projects not listed (furthest or smallest).
Postcode districts in North Yorkshire
| District | Projects within 10 km | Pending | Approved | Operational |
|---|---|---|---|---|
| BD23 | 10 | 1 | 3 | 3 |
| BD24 | 0 | 0 | 0 | 0 |
| DL6 | 10 | 3 | 2 | 1 |
| DL7 | 16 | 4 | 6 | 2 |
| DL8 | 3 | 0 | 3 | 0 |
| DL9 | 11 | 2 | 6 | 3 |
| DL10 | 14 | 2 | 9 | 3 |
| DL11 | 2 | 1 | 0 | 0 |
| HG1 | 24 | 6 | 13 | 2 |
| HG2 | 24 | 6 | 13 | 2 |
| HG3 | 21 | 4 | 11 | 2 |
| HG4 | 13 | 1 | 7 | 3 |
| HG5 | 23 | 3 | 18 | 1 |
| LS24 | 16 | 5 | 6 | 3 |
| TS9 | 8 | 0 | 3 | 3 |
| YO7 | 5 | 1 | 1 | 3 |
| YO8 | 31 | 3 | 19 | 3 |
| YO11 | 8 | 0 | 6 | 0 |
| YO12 | 9 | 1 | 6 | 0 |
| YO13 | 7 | 0 | 5 | 0 |
| YO14 | 13 | 2 | 10 | 0 |
| YO17 | 8 | 0 | 8 | 0 |
| YO18 | 0 | 0 | 0 | 0 |
| YO21 | 4 | 1 | 3 | 0 |
| YO22 | 4 | 1 | 3 | 0 |
| YO51 | 18 | 4 | 12 | 1 |
| YO60 | 5 | 2 | 2 | 1 |
| YO61 | 12 | 1 | 7 | 4 |
| YO62 | 2 | 0 | 2 | 0 |
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to North Yorkshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.