Solar, wind and battery projects near York (YO51)
18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of YO51 (North Yorkshire): 4 are waiting for a planning decision, 12 approved but not yet running, 1 operational. The largest live scheme is Low Moor Lane, Scotton (200 MW battery storage, application submitted on 16 December 2025, no decision recorded), 9.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of YO51
Projects of 1 MW and more (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wormald Green Solar Farmsolar farm | solar farm | 43 | approved, not builtupdated Mar 2026 | Dec 2023 | granted Jul 2025 | Mar 2026 | North Yorkshire | 7.4 |
| New Oaks, Station Roadbattery storage | battery storage | 50 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | North Yorkshire | 8.4 |
| Wormald Greenbattery storage | battery storage | 33 | operationalupdated Feb 2026 | Mar 2022 | granted Jun 2022 | Feb 2026 | North Yorkshire | 8.5 |
| Burton Top Farmsolar farm | solar farm | 3.6 | abandonedupdated Mar 2019 | Sep 2015 | granted Nov 2015 | Mar 2019 | North Yorkshire | 8.7 |
| Pilmoor Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated May 2026 | Nov 2023 | granted Sep 2024 | May 2026 | North Yorkshire | 9.2 |
| Low Moor Lane, Scottonbattery storage | battery storage | 200 | application submittedupdated Mar 2026 | Dec 2025 | — | Mar 2026 | North Yorkshire | 9.5 |
| Station Lane, South Stainleysolar farm | solar farm | 10 | approved, not builtupdated May 2024 | Nov 2022 | granted Apr 2024 | May 2024 | North Yorkshire | 9.5 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Barneby Way, Boroughbridgesolar farm | solar farm | 0.3 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Aug 2024 | Aug 2024 | North Yorkshire | 0.3 |
| Limebar Lane Energy Distribution Centresolar farm | solar farm | — | under constructionupdated Mar 2021 | Jan 2021 | granted Aug 2022 | Mar 2021 | North Yorkshire | 3.4 |
| Newby Hall Estate, The Stablesrooftop solar | rooftop solar | 0.1 | approved, not built may be out of dateupdated Jun 2023 | Apr 2023 | granted Jun 2023 | Jun 2023 | North Yorkshire | 5.1 |
| Rabbit Hill Park, Allerton Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2023 | Feb 2023 | granted Mar 2023 | Mar 2023 | North Yorkshire | 5.1 |
| Wormald Green Solar Farmbattery storage | battery storage | — | approved, not builtupdated Mar 2026 | Dec 2023 | granted Jul 2025 | Mar 2026 | North Yorkshire | 7.4 |
| Pond View Farm, Tholthorpesolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated May 2023 | Feb 2022 | granted May 2023 | May 2023 | North Yorkshire | 7.7 |
| Ripon Community Leisure Centre, Dallamires Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Jan 2026 | Mar 2026 | North Yorkshire | 8.9 |
| Lawrence House Farm Solar Farmsolar farm | solar farm | — | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | North Yorkshire | 9.5 |
| Lawrence House Farm Solar Farmbattery storage | battery storage | — | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | North Yorkshire | 9.5 |
| Flaxby Moor Works, Flaxbyrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2021 | Jul 2021 | granted Sep 2021 | Sep 2021 | North Yorkshire | 9.5 |
| Station Lane, South Stainleybattery storage | battery storage | — | approved, not builtupdated May 2024 | Nov 2022 | granted Apr 2024 | May 2024 | North Yorkshire | 9.5 |
Distance from the average position of the YO51 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 1 | 6 | 0 | 0 | 104 |
| Rooftop solar | 4 | 0 | 4 | 0 | 0 | 0.9 |
| Battery storage | 6 | 3 | 2 | 1 | 0 | 250 |
MW in pipeline: pending, approved and under-construction capacity.
How North Yorkshire decides solar, wind and battery applications
| Applications | North Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 165 | 10,236 |
| Refused | 28 (17%) | 19% |
| Solar refused | 15 of 112 | 12% |
| Onshore wind refused | 8 of 24 | 45% |
| Battery storage refused | 5 of 29 | 16% |
| Median time from submission to decision | 15.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 13 / 12 | — |
All projects in North Yorkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near YO51, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.