Energy Projects Near You

Pilmoor Solar Farm (50 MW)

Pilmoor Solar Farm is a 50 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 11 September 2024, not yet built; the record was last updated on 7 May 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
approved, not builtstatus in REPD
7 May 2026record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
29 November 2023Application submitted
11 September 2024Planning permission granted

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
7 May 2026
Operator or applicant
Stark Energy
Planning authority
North Yorkshire
Planning application reference
ZB23/02461/FUL
Site area
94.4 ha
Address (REPD)
OS Field 5220 Brafferton
Council area (by location)
North Yorkshire
Time to decision
41 weeks
Contracts for Difference
AR7a
REPD reference
15452

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Cold Harbour Farmsolar farm5operational2.8
Land South of Highfield Housesolar farm5operational4.0
York Solar Farmsolar farm34.7operational4.3
Boscar Grange Farmbattery storage27operational4.3
Os Field, Husthwaitesolar farm49.9approved, not built4.8
Boscar Layby, Raskelfsolar farm30application submitted5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1481, -1.2945).