Energy Projects Near You

Boscar Grange Farm (27 MW battery storage)

Boscar Grange Farm is a 27 MW battery storage project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 December 2019; the record was last updated on 18 December 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWbattery storage
operationalstatus in REPD
18 December 2019record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
29 October 2018Application submitted
23 May 2019Construction started
18 December 2019Operational

Project details

Technology
battery storage (co-located with re)
Capacity
27 MW
Status (REPD)
operational
Record last updated
18 December 2019
Operator or applicant
Gridserve
Planning authority
North Yorkshire
Planning application reference
18/02314/NMC
Address (REPD)
Boscar Grange Farm, Thirsk Road, Easingwold, York, North Yorkshire
Council area (by location)
North Yorkshire
REPD reference
7332

Recorded together with York Solar Farm (34.7 MW solar farm, operational).

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land South of Highfield Housesolar farm5operational0.5
Boscar Layby, Raskelfsolar farm30application submitted1.5
Os Field, Husthwaitesolar farm49.9approved, not built1.6
Pilmoor Solar Farmsolar farm50approved, not built4.3
Cold Harbour Farmsolar farm5operational6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1445, -1.2281).