Energy Projects Near You

York Solar Farm (34.7 MW)

York Solar Farm is a 34.7 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 December 2019; the record was last updated on 28 May 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

34.7 MWsolar farm
operationalstatus in REPD
28 May 2020record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
5 June 2015Application submitted
21 September 2015Planning permission granted
23 May 2019Construction started
18 December 2019Operational

Project details

Technology
solar farm
Capacity
34.7 MW
Status (REPD)
operational
Record last updated
28 May 2020
Operator or applicant
Gridserve
Planning authority
North Yorkshire
Planning application reference
15/01268/FUL
Site area
74.0 ha
Address (REPD)
Boscar Grange Farm, Thirsk Road, Easingwold, York, North Yorkshire
Council area (by location)
North Yorkshire
Time to decision
15 weeks
REPD reference
5482

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Boscar Grange Farmbattery storage27operational<0.1
Land South of Highfield Housesolar farm5operational0.5
Boscar Layby, Raskelfsolar farm30application submitted1.5
Os Field, Husthwaitesolar farm49.9approved, not built1.6
Pilmoor Solar Farmsolar farm50approved, not built4.3
Cold Harbour Farmsolar farm5operational6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1445, -1.2281).