Os Field, Husthwaite (49.9 MW solar farm)

Os Field, Husthwaite is a 49.9 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 October 2025, not yet built; the record was last updated on 7 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
7 November 2025record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
29 September 2023Application submitted
4 November 2024Refused by the planning authority
25 April 2025Appeal lodged
14 October 2025Planning permission granted
14 October 2025Appeal allowed
14 October 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
7 November 2025
Operator or applicant
Woolpots Solar Farm Limited
Planning authority
North Yorkshire
Planning application reference
ZB23/02015/FUL
Appeal reference
25/00013/REFUSE
Site area
51.0 ha
Address (REPD)
OS Field 2700 Carlton Husthwaite
Council area (by location)
North Yorkshire
Time to decision
107 weeks
Name in REPD
Os Field, Husthwaite - Solar Photovoltaic Array
REPD reference
15548

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Earlier applications for this site

ApplicationMWSubmittedOutcome
Os Field, Husthwaite 21/03042/FUL49.923 December 2021replaced by a revised application

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land South of Highfield Housesolar farm5operational1.3
Boscar Grange Farmbattery storage27operational1.6
York Solar Farmsolar farm34.7operational1.6
Boscar Layby, Raskelfsolar farm30application submitted2.9
Pilmoor Solar Farmsolar farm50approved, not built4.8
Cold Harbour Farmsolar farm5operational6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (54.1585, -1.2232).