Solar, wind and battery projects near York (YO61)
12 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of YO61 (North Yorkshire): 1 is waiting for a planning decision, 7 approved but not yet running, 4 operational. The largest live scheme is Pilmoor Solar Farm (50 MW solar farm, approved on 11 September 2024, not yet built), 7.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of YO61
Projects of 1 MW and more (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Boscar Layby, Raskelfsolar farm | solar farm | 30 | application submittedupdated Jun 2025 | May 2025 | — | Jun 2025 | North Yorkshire | 2.2 |
| York Solar Farmsolar farm | solar farm | 34.7 | operationalupdated May 2020 | Jun 2015 | granted Sep 2015 | May 2020 | North Yorkshire | 3.7 |
| Boscar Grange Farmbattery storage | battery storage | 27 | operationalupdated Dec 2019 | Oct 2018 | — | Dec 2019 | North Yorkshire | 3.7 |
| Land South of Highfield Housesolar farm | solar farm | 5 | operationalupdated Aug 2016 | Feb 2015 | granted Jun 2015 | Aug 2016 | North Yorkshire | 4.2 |
| Os Field, Husthwaitesolar farm | solar farm | 49.9 | approved, not builtupdated Nov 2025 | Sep 2023 | granted Oct 2025 | Nov 2025 | North Yorkshire | 4.9 |
| Pilmoor Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated May 2026 | Nov 2023 | granted Sep 2024 | May 2026 | North Yorkshire | 7.3 |
| Cold Harbour Farmsolar farm | solar farm | 5 | operationalupdated Dec 2015 | Nov 2014 | granted Feb 2015 | Dec 2015 | North Yorkshire | 9.7 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Rose Cottage, Easingwold To Craykerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Feb 2025 | Mar 2025 | North Yorkshire | 2.4 |
| Brickworks Forest Lane, Alnerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2024 | Oct 2024 | granted Dec 2024 | Dec 2024 | North Yorkshire | 3.1 |
| Os Field, Husthwaitebattery storage | battery storage | — | approved, not builtupdated Nov 2025 | Sep 2023 | granted Oct 2025 | Nov 2025 | North Yorkshire | 4.9 |
| Pond View Farm, Tholthorpesolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated May 2023 | Feb 2022 | granted May 2023 | May 2023 | North Yorkshire | 5.8 |
| Wildon grange, Mill Field Lanesolar farm | solar farm | 0.5 | approved, not built may be out of dateupdated Mar 2023 | Sep 2022 | granted Mar 2023 | Mar 2023 | North Yorkshire | 9.0 |
Distance from the average position of the YO61 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 1 | 4 | 3 | 0 | 131 |
| Rooftop solar | 2 | 0 | 2 | 0 | 0 | 0.8 |
| Battery storage | 2 | 0 | 1 | 1 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How North Yorkshire decides solar, wind and battery applications
| Applications | North Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 165 | 10,236 |
| Refused | 28 (17%) | 19% |
| Solar refused | 15 of 112 | 12% |
| Onshore wind refused | 8 of 24 | 45% |
| Battery storage refused | 5 of 29 | 16% |
| Median time from submission to decision | 15.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 13 / 12 | — |
All projects in North Yorkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near YO61, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.