Energy Projects Near You

Solar, wind and battery projects near York (YO60)

5 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of YO60 (North Yorkshire): 2 are waiting for a planning decision, 2 approved but not yet running, 1 operational. The largest live scheme is White Barn Farm, Station Road (1.7 MW wind farm, application submitted on 1 April 2026, no decision recorded), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5projects within 10 km
2awaiting a decision
2approved, not running
1operational

Projects within 10 km of YO60

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Mill Hill Farmsolar farmsolar farm5operationalupdated Dec 2015Apr 2015granted Jul 2015Dec 2015North Yorkshire6.2
White Barn Farm, Station Roadwind farmwind farm1.7application submittedApr 2026——North Yorkshire7.9
Smaller schemes under 1 MW, mostly rooftop solar (3)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Walbutts Sewage Works, Brecks Lanesolar farmsolar farm0.3approved, not builtupdated Oct 2023Jun 2023granted Sep 2023Oct 2023York6.6
Well Lane, Sutton-On-The-Forest Solar Array &110KW Battery Storagesolar farmsolar farm0.6application submittedupdated May 2026Feb 2026—May 2026North Yorkshire7.7
Malton Wastewater Treatment Works, Seven Lane Solar Panelssolar farmsolar farm0.2approved, not builtupdated Nov 2023Jun 2023granted Nov 2023Nov 2023North Yorkshire9.4

Distance from the average position of the YO60 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm412101.1
Wind farm110001.7

MW in pipeline: pending, approved and under-construction capacity.

How North Yorkshire decides solar, wind and battery applications

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

All projects in North Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.