Energy Projects Near You

Solar, wind and battery projects near Malton (YO17)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of YO17 (North Yorkshire): 8 approved but not yet running. The largest live scheme is Third Energy UK Gas Limited (100 MW battery storage, approved on 14 October 2021, not yet built; REPD status may be out of date), 9.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
0awaiting a decision
8approved, not running
0operational

Projects within 10 km of YO17

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Showfield Lanebattery storagebattery storage5approved, not built may be out of dateupdated Dec 2023Nov 2018granted Feb 2019Dec 2023North Yorkshire2.7
Windmill Farm Solar Farm (Old Malton)solar farmsolar farm30.4approved, not builtupdated Feb 2026Jan 2023refused Oct 2023Feb 2026North Yorkshire3.8
Windmill Farm Solar Farm (Old Malton)battery storagebattery storage12.6approved, not builtupdated Feb 2026Jan 2023granted Feb 2025Feb 2026North Yorkshire3.8
Third Energy UK Gas Limitedbattery storagebattery storage100approved, not built may be out of dateupdated Mar 2023Aug 2021granted Oct 2021Mar 2023North Yorkshire9.0
Smaller schemes under 1 MW, mostly rooftop solar (4)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Cranswick Gourmet Pastry, Hugden Wayrooftop solarrooftop solar0.7approved, not builtupdated Dec 2022Oct 2022granted Dec 2022Dec 2022North Yorkshire0.8
Malton And Norton District Hospital, Hospital Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2026Dec 2025granted Jan 2026Feb 2026North Yorkshire3.2
Malton Wastewater Treatment Works, Seven Lane Solar Panelssolar farmsolar farm0.2approved, not builtupdated Nov 2023Jun 2023granted Nov 2023Nov 2023North Yorkshire3.8
Linton Mill, Main Streetrooftop solarrooftop solar0.5approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025North Yorkshire6.4

Distance from the average position of the YO17 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2020030.6
Rooftop solar303001.3
Battery storage30300118

MW in pipeline: pending, approved and under-construction capacity.

How North Yorkshire decides solar, wind and battery applications

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

All projects in North Yorkshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near YO17, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.