Solar, wind and battery projects near York (YO30)
38 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of YO30 (York): 8 are waiting for a planning decision, 27 approved but not yet running, 2 operational. The largest live scheme is East York Energy Hub (250 MW battery storage, approved on 15 September 2025, not yet built), 6.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of YO30
Projects of 1 MW and more (13)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Overton Grange, Overton Road Solar Farm Battery Energy Storagesolar farm | solar farm | 49.9 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | North Yorkshire | 3.3 |
| Poppleton Solar Farmsolar farm | solar farm | 32.6 | approved, not builtupdated Dec 2024 | Dec 2023 | granted Oct 2024 | Dec 2024 | York | 4.3 |
| Sutton-on-the-Forest, Brownmoor Lane Solar Parksolar farm | solar farm | 49.9 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 | York | 5.1 |
| Sutton-on-the-Forest, Brownmoor Lane -BESSbattery storage | battery storage | 10 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 | York | 5.1 |
| Harewood Whin, Tinker Lane Solar Farmsolar farm | solar farm | 28 | approved, not builtupdated May 2025 | Oct 2023 | granted Apr 2025 | May 2025 | York | 5.2 |
| Hessay Solar Farmsolar farm | solar farm | 40 | approved, not builtupdated Mar 2024 | Apr 2023 | granted Mar 2024 | Mar 2024 | York | 5.5 |
| Monets Garden Battery, Osbaldwick Energy Storage Facilitybattery storage | battery storage | 50 | approved, not builtupdated May 2025 | Oct 2024 | granted Mar 2025 | May 2025 | York | 6.2 |
| East York Energy Hubbattery storage | battery storage | 250 | approved, not builtupdated Oct 2025 | Dec 2024 | granted Sep 2025 | Oct 2025 | York | 6.7 |
| Osbaldwick Substationbattery storage | battery storage | 49.9 | operationalupdated May 2025 | Aug 2020 | granted Oct 2020 | May 2025 | York | 7.2 |
| Meadowville, Hull Roadbattery storage | battery storage | 48 | approved, not builtupdated Dec 2025 | Jul 2025 | granted Oct 2025 | Dec 2025 | York | 7.4 |
| Naburn Sewage Treatment Workssolar farm | solar farm | 1.4 | refusedupdated Jan 2016 | Aug 2015 | refused Dec 2015 | Jan 2016 | York | 8.4 |
| Green Lane, Moor Monkton Solar Panels & Battery Energy Storage Systemsolar farm | solar farm | 49.9 | application submittedupdated Aug 2025 | Apr 2025 | — | Aug 2025 | North Yorkshire | 8.5 |
| White Barn Farm, Station Roadwind farm | wind farm | 1.7 | application submitted | Apr 2026 | — | — | North Yorkshire | 8.7 |
Smaller schemes under 1 MW, mostly rooftop solar (25)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Arnold Clark Limited, Great North Wayrooftop solar | rooftop solar | 0.3 | application submittedupdated May 2026 | Jan 2026 | — | May 2026 | York | 1.4 |
| Kingswayrooftop solar | rooftop solar | 0.2 | operationalupdated May 2022 | May 2022 | granted Dec 2022 | May 2022 | York | 2.2 |
| St Peters School, Cliftonrooftop solar | rooftop solar | 0.1 | approved, not built may be out of dateupdated Jul 2023 | May 2023 | granted Jul 2023 | Jul 2023 | York | 2.8 |
| York District Hospital, Wigginton Roadrooftop solar | rooftop solar | 0.6 | application submittedupdated Jan 2026 | Dec 2025 | — | Jan 2026 | York | 2.9 |
| Yearsley Swimming Baths, Haleys Terracerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Nov 2025 | Jan 2026 | York | 3.1 |
| Network Rail National Delivery Service, Holgate Roadrooftop solar | rooftop solar | 0.5 | approved, not built may be out of dateupdated Apr 2023 | Feb 2023 | granted Apr 2023 | Apr 2023 | York | 3.4 |
| Network Rail National Delivery Service, Holgate Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Feb 2023 | Dec 2022 | granted Feb 2023 | Feb 2023 | York | 3.4 |
| Newlands Farm, Wiggintonrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | York | 4.0 |
| Sainsburys supermarket, Monks Cross Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Oct 2024 | Aug 2024 | granted Oct 2024 | Oct 2024 | York | 4.2 |
| Better York Leisure Centre, Kathryn Avenuerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Jul 2025 | granted Aug 2025 | Aug 2025 | York | 4.2 |
| Westfield Community Primary School, Askham Lane Solar PV Systemsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2023 | May 2023 | granted Jul 2023 | Jun 2023 | York | 4.4 |
| Applefields School, Bad Bargain Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2024 | Jun 2024 | granted Aug 2024 | Sep 2024 | York | 5.2 |
| Longfield Grange, York Road Solar PV Arrayssolar farm | solar farm | 0.2 | approved, not builtupdated Oct 2025 | Jul 2025 | granted Oct 2025 | Oct 2025 | York | 5.3 |
| Donald Baron Court, Heslingtonrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | York | 5.8 |
| Biology Department, Wentworth Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | York | 6.0 |
| Computer Science D Block University Of York, University Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Aug 2024 | Aug 2024 | York | 6.0 |
| David Lloyd Clubs, Windmill Lanerooftop solar | rooftop solar | — | approved, not builtupdated Nov 2025 | Jul 2025 | granted Oct 2025 | Nov 2025 | York | 6.1 |
| Windmill Lanerooftop solar | rooftop solar | — | approved, not builtupdated Apr 2026 | Jan 2026 | granted Mar 2026 | Apr 2026 | York | 6.1 |
| Archbishop Holgates School, Hull Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2023 | May 2023 | granted Jul 2023 | Jun 2023 | York | 6.3 |
| The York Management School Church Lane, Innovation Way Solar Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Aug 2024 | Jul 2024 | granted Aug 2024 | Aug 2024 | York | 6.4 |
| York Collegerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2025 | Mar 2025 | granted May 2025 | Jun 2025 | York | 6.4 |
| Green Lane, Moor Monkton Solar Panels & Battery Energy Storage Systembattery storage | battery storage | — | application submittedupdated Aug 2025 | Apr 2025 | — | Aug 2025 | North Yorkshire | 8.5 |
| R S Cockerill York Limited, Stamford Bridge Roadrooftop solar | rooftop solar | 0.7 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Oct 2025 | Nov 2025 | York | 9.2 |
| Yorkshire Water Naburn, Naburn Lane - Ground Mounted Solar Arraysolar farm | solar farm | 0.4 | approved, not builtupdated Jun 2025 | Mar 2025 | granted May 2025 | Jun 2025 | York | 9.3 |
| Walbutts Sewage Works, Brecks Lanesolar farm | solar farm | 0.3 | approved, not builtupdated Oct 2023 | Jun 2023 | granted Sep 2023 | Oct 2023 | York | 9.4 |
Distance from the average position of the YO30 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 3 | 6 | 0 | 1 | 251 |
| Rooftop solar | 21 | 2 | 18 | 1 | 0 | 5.9 |
| Wind farm | 1 | 1 | 0 | 0 | 0 | 1.7 |
| Battery storage | 6 | 2 | 3 | 1 | 0 | 358 |
MW in pipeline: pending, approved and under-construction capacity.
How York decides solar, wind and battery applications
| Applications | York | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 38 | 10,236 |
| Refused | 4 (11%) | 19% |
| Solar refused | 2 of 31 | 12% |
| Battery storage refused | 2 of 7 | 16% |
| Median time from submission to decision | 8.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near YO30, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.