Harewood Whin, Tinker Lane Solar Farm (28 MW)

Harewood Whin, Tinker Lane Solar Farm is a 28 MW solar farm project in York, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 April 2025, not yet built; the record was last updated on 20 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

28 MWsolar farm
approved, not builtstatus in REPD
20 May 2025record last updated
Yorkcouncil area

Planning timeline

DateStage
26 October 2023Application submitted
28 April 2025Planning permission granted
28 April 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
28 MW
Status (REPD)
approved, not built
Record last updated
20 May 2025
Operator or applicant
Yorwaste Limited
Planning authority
York
Planning application reference
23/01732/FULM
Site area
82.5 ha
Address (REPD)
Harewood Whin, Tinker Lane, Rufforth, York
Council area (by location)
York
Time to decision
79 weeks
Name in REPD
Harewood Whin, Tinker Lane - Solar Farm
REPD reference
15267

Who decides

ApplicationsYorkUK
Decided applications (solar, wind, battery)3810,236
Refused4 (11%)19%
Solar refused2 of 3112%
Battery storage refused2 of 716%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hessay Solar Farmsolar farm40approved, not built2.0
Poppleton Solar Farmsolar farm32.6approved, not built4.1
Overton Grange, Overton Road Solar Farm Battery Energy Storagesolar farm49.9application submitted5.0
Green Lane, Moor Monkton Solar Panels & Battery Energy Storage Systemsolar farm49.9application submitted5.2
Sutton-on-the-Forest, Brownmoor Lane -BESSbattery storage10application submitted9.2
Sutton-on-the-Forest, Brownmoor Lane Solar Parksolar farm49.9application submitted9.2
Monets Garden Battery, Osbaldwick Energy Storage Facilitybattery storage50approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.9592, -1.1801).