Energy Projects Near You

Monets Garden Battery, Osbaldwick Energy Storage Facility (50 MW)

Monets Garden Battery, Osbaldwick Energy Storage Facility is a 50 MW battery storage project in York, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 March 2025, not yet built; the record was last updated on 6 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWbattery storage
approved, not builtstatus in REPD
6 May 2025record last updated
Yorkcouncil area

Planning timeline

DateStage
29 October 2024Application submitted
28 March 2025Planning permission granted
28 March 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
6 May 2025
Operator or applicant
Monets Garden Battery Limited
Planning authority
York
Planning application reference
24/01851/FULM
Address (REPD)
The National Grid Substation, Osbaldwick Link Road, Osbaldwick, York
Council area (by location)
York
Time to decision
21 weeks
Name in REPD
Monets Garden Battery, Osbaldwick - Energy Storage Facility
REPD reference
17496

Who decides

ApplicationsYorkUK
Decided applications (solar, wind, battery)3810,236
Refused4 (11%)19%
Solar refused2 of 3112%
Battery storage refused2 of 716%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
East York Energy Hubbattery storage250approved, not built0.6
Osbaldwick Substationbattery storage49.9operational1.1
Meadowville, Hull Roadbattery storage48approved, not built1.3
Murton Waybattery storage100approved, not built8.3
Harewood Whin, Tinker Lane Solar Farmsolar farm28approved, not built9.5
Overton Grange, Overton Road Solar Farm Battery Energy Storagesolar farm49.9application submitted9.5
Sutton-on-the-Forest, Brownmoor Lane Solar Parksolar farm49.9application submitted9.8
Sutton-on-the-Forest, Brownmoor Lane -BESSbattery storage10application submitted9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.9593, -1.0354).