East York Energy Hub (250 MW battery storage)

East York Energy Hub is a 250 MW battery storage project in York, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 15 September 2025, not yet built; the record was last updated on 7 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

250 MWbattery storage
approved, not builtstatus in REPD
7 October 2025record last updated
Yorkcouncil area

Planning timeline

DateStage
19 December 2024Application submitted
15 September 2025Planning permission granted
15 September 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
250 MW
Status (REPD)
approved, not built
Record last updated
7 October 2025
Operator or applicant
York Energy Park Limited
Planning authority
York
Planning application reference
24/02303/FULM
Address (REPD)
Adjacent To Gells Farm, Murton Way, York
Council area (by location)
York
Time to decision
39 weeks
REPD reference
10583

Who decides

ApplicationsYorkUK
Decided applications (solar, wind, battery)3810,236
Refused4 (11%)19%
Solar refused2 of 3112%
Battery storage refused2 of 716%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Osbaldwick Substationbattery storage49.9operational0.5
Monets Garden Battery, Osbaldwick Energy Storage Facilitybattery storage50approved, not built0.6
Meadowville, Hull Roadbattery storage48approved, not built0.7
Murton Waybattery storage100approved, not built8.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.9589, -1.0266).