Murton Way (100 MW battery storage)

Murton Way is a 100 MW battery storage project in York, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 July 2025, not yet built; the record was last updated on 29 July 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
29 July 2025record last updated
Yorkcouncil area

Planning timeline

DateStage
22 August 2023Application submitted
17 July 2025Planning permission granted
17 July 2025Appeal allowed
17 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
29 July 2025
Operator or applicant
First Way Solar Limited
Planning authority
York
Planning application reference
25/00743/FULM
Address (REPD)
North W/O Murton Way, York
Council area (by location)
York
Time to decision
99 weeks
Name in REPD
Murton Way - Battery Energy Storage
REPD reference
18767

Earlier applications for this site

ApplicationMWSubmittedOutcome
Murton Way 23/02030/FULM10021 November 2023refused 9 December 2024

Who decides

ApplicationsYorkUK
Decided applications (solar, wind, battery)3810,236
Refused4 (11%)19%
Solar refused2 of 3112%
Battery storage refused2 of 716%
Median time from submission to decision8.0 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Redmoor Farmsolar farm25.5permission expired6.1
Meadowville, Hull Roadbattery storage48approved, not built7.5
Osbaldwick Substationbattery storage49.9operational7.7
East York Energy Hubbattery storage250approved, not built8.0
Monets Garden Battery, Osbaldwick Energy Storage Facilitybattery storage50approved, not built8.3
Ryedale Farm, Seaton Common Lanebattery storage300approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8945, -0.9712).