Redmoor Farm (25.5 MW solar farm)
Redmoor Farm is a 25.5 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 27 January 2020; the record was last updated on 3 September 2020.
25.5 MWsolar farm
permission expiredstatus in REPD
3 September 2020record last updated
North Yorkshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 21 August 2015 | Application submitted |
| 27 January 2017 | Planning permission granted |
| 27 January 2020 | Permission expired |
Project details
- Technology
- solar farm
- Capacity
- 25.5 MW
- Status (REPD)
- permission expired
- Record last updated
- 3 September 2020
- Operator or applicant
- TGC Renewables
- Planning authority
- North Yorkshire
- Planning application reference
- 2015/0967/FUL
- Site area
- 55.4 ha
- Address (REPD)
- Redmoor Farm, Skipwith Common Road, North Duffield, Selby
- Council area (by location)
- North Yorkshire
- Time to decision
- 75 weeks
- REPD reference
- 5929
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Redmoor Farm 2014/1150/FUL | 25.5 | 18 November 2014 | refused 15 June 2015 |
Who decides
| Applications | North Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 165 | 10,236 |
| Refused | 28 (17%) | 19% |
| Solar refused | 15 of 112 | 12% |
| Onshore wind refused | 8 of 24 | 45% |
| Battery storage refused | 5 of 29 | 16% |
| Median time from submission to decision | 15.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 13 / 12 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Osgodby Grange, Osgodby Solar Energy | solar farm | 49.9 | approved, not built | 5.4 |
| Murton Way | battery storage | 100 | approved, not built | 6.1 |
| Hull Road, Lund | battery storage | 40 | approved, not built | 6.7 |
| Cleek Hall | wind farm | 15 | abandoned | 7.3 |
| Newlands Farm, Turnham Lane | solar farm | 49.9 | application submitted | 7.7 |
| Barlow Road, Barlow Road | battery storage | 80 | application withdrawn | 9.1 |
| Ryedale Farm, Seaton Common Lane | battery storage | 300 | approved, not built | 9.6 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.8394, -0.9752).