Solar, wind and battery projects near Selby (YO8)
31 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of YO8 (North Yorkshire): 3 are waiting for a planning decision, 19 approved but not yet running, 3 operational. The largest live scheme is Eggborough Battery Energy Storage System (550 MW battery storage, approved on 30 May 2025, not yet built), 9.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of YO8
Projects of 1 MW and more (24)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Barlow Road, Barlow Roadbattery storage | battery storage | 80 | application withdrawnupdated Mar 2025 | Aug 2023 | — | Mar 2025 | North Yorkshire | 0.9 |
| Newlands Farm, Turnham Lanesolar farm | solar farm | 49.9 | application submittedupdated Nov 2025 | Jul 2025 | — | Nov 2025 | North Yorkshire | 2.0 |
| Cleek Hallwind farm | wind farm | 15 | abandonedupdated Sep 2015 | Aug 2009 | granted Sep 2012 | Sep 2015 | North Yorkshire | 3.2 |
| Osgodby Grange, Osgodby Solar Energysolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Mar 2026 | Sep 2021 | granted Jul 2022 | Mar 2026 | North Yorkshire | 3.5 |
| Hull Road, Lundbattery storage | battery storage | 40 | approved, not builtupdated Jan 2025 | Jul 2024 | granted Jan 2025 | Jan 2025 | North Yorkshire | 3.8 |
| Scalm Park, Wistow Solar Farm & Battery Energy Storagesolar farm | solar farm | 49.9 | approved, not builtupdated Sep 2025 | Nov 2024 | granted Sep 2025 | Sep 2025 | North Yorkshire | 5.5 |
| Scalm Park / Bishopwoodwind farm | wind farm | 17.5 | appeal withdrawnupdated Aug 2018 | Jul 2009 | refused Jan 2013 | Aug 2018 | North Yorkshire | 5.5 |
| Camblesforth Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Feb 2021 | Jun 2021 | granted Jul 2022 | Feb 2021 | North Yorkshire | 5.7 |
| Drax Re-Powerbattery storage | battery storage | 200 | approved, not builtupdated Jan 2020 | Feb 2018 | granted May 2018 | Jan 2020 | North Yorkshire | 6.9 |
| Broad Lane, Cawood Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | North Yorkshire | 7.0 |
| Broad Lane, Cawood Solar Farm & Battery Storagebattery storage | battery storage | 10 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 | North Yorkshire | 7.0 |
| Lakeside Energy Storage Facilitybattery storage | battery storage | 99.9 | approved, not built may be out of dateupdated Dec 2021 | Dec 2020 | granted May 2021 | Dec 2021 | North Yorkshire | 7.1 |
| Escrick Park Community Power Projectwind farm | wind farm | 4.6 | application withdrawnupdated Jun 2011 | — | — | Jun 2011 | North Yorkshire | 7.3 |
| Helios Renewable Energy Projectsolar farm | solar farm | 190 | approved, not builtupdated Dec 2025 | Jul 2024 | granted Dec 2025 | Dec 2025 | North Yorkshire | 7.6 |
| Hales Lanebattery storage | battery storage | 100 | approved, not built may be out of dateupdated May 2022 | Sep 2021 | granted May 2022 | May 2022 | North Yorkshire | 7.9 |
| Station Road, Carltonbattery storage | battery storage | 99 | approved, not builtupdated Jun 2025 | Oct 2024 | granted May 2025 | Jun 2025 | North Yorkshire | 8.0 |
| Carlton Solar Farmsolar farm | solar farm | 50 | approved, not builtupdated Feb 2026 | Feb 2023 | granted Apr 2024 | Feb 2026 | North Yorkshire | 8.0 |
| Loftsome Bridgewind farm | wind farm | 1.3 | operationalupdated Aug 2017 | Jun 2006 | granted Jan 2007 | Aug 2017 | North Yorkshire | 8.5 |
| Redmoor Farmsolar farm | solar farm | 25.5 | permission expiredupdated Sep 2020 | Aug 2015 | granted Jan 2017 | Sep 2020 | North Yorkshire | 8.6 |
| Eggborough Power Station, Selby Roadbattery storage | battery storage | 500 | approved, not built may be out of dateupdated Sep 2025 | Oct 2022 | granted Jan 2023 | Sep 2025 | North Yorkshire | 8.8 |
| Rusholme Wind Farmwind farm | wind farm | 24 | operationalupdated Dec 2014 | Jul 2004 | granted Oct 2006 | Dec 2014 | North Yorkshire | 9.3 |
| Wood Lanewind farm | wind farm | 32.2 | application withdrawnupdated Jan 2016 | Jul 2009 | — | Jan 2016 | North Yorkshire | 9.5 |
| Eggborough Battery Energy Storage Systembattery storage | battery storage | 550 | approved, not builtupdated Jul 2025 | Jun 2024 | granted May 2025 | Jul 2025 | North Yorkshire | 9.6 |
| Rusholme Grangebattery storage | battery storage | 40 | operationalupdated Aug 2024 | May 2021 | granted Sep 2021 | Aug 2024 | North Yorkshire | 9.8 |
Smaller schemes under 1 MW, mostly rooftop solar (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Aldi Stores, Portholme Roadrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Nov 2024 | granted Dec 2024 | Jan 2025 | North Yorkshire | 0.4 |
| Selby War Memorial Hospital, Doncaster Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Jan 2026 | Apr 2026 | North Yorkshire | 1.2 |
| Selby Garden And Pet Centre, Hull Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | North Yorkshire | 2.6 |
| Hull Roadbattery storage | battery storage | — | approved, not builtupdated Nov 2023 | May 2023 | granted Nov 2023 | Nov 2023 | North Yorkshire | 2.7 |
| Scalm Park, Wistow Solar Farm & Battery Energy Storagebattery storage | battery storage | — | approved, not builtupdated Sep 2025 | Nov 2024 | granted Sep 2025 | Sep 2025 | North Yorkshire | 5.5 |
| Helios Renewable Energy Projectbattery storage | battery storage | — | approved, not builtupdated Dec 2025 | Jul 2024 | granted Dec 2025 | Dec 2025 | North Yorkshire | 7.6 |
| Carlton Solar Farmbattery storage | battery storage | — | approved, not builtupdated Dec 2024 | Feb 2023 | granted Apr 2024 | Dec 2024 | North Yorkshire | 8.0 |
Distance from the average position of the YO8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 2 | 5 | 0 | 0 | 489 |
| Rooftop solar | 3 | 0 | 3 | 0 | 0 | 0.5 |
| Wind farm | 6 | 0 | 0 | 2 | 0 | 0 |
| Battery storage | 14 | 1 | 11 | 1 | 0 | 1,599 |
MW in pipeline: pending, approved and under-construction capacity.
How North Yorkshire decides solar, wind and battery applications
| Applications | North Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 165 | 10,236 |
| Refused | 28 (17%) | 19% |
| Solar refused | 15 of 112 | 12% |
| Onshore wind refused | 8 of 24 | 45% |
| Battery storage refused | 5 of 29 | 16% |
| Median time from submission to decision | 15.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 13 / 12 | — |
All projects in North Yorkshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near YO8, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.