Cleek Hall (15 MW wind farm)

Cleek Hall is a 15 MW wind farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 29 September 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
abandonedstatus in REPD
29 September 2015record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
17 August 2009Application submitted
9 November 2011Refused by the planning authority
18 September 2012Planning permission granted
18 September 2012Appeal allowed
18 September 2017Permission expired

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
abandoned
Record last updated
29 September 2015
Operator or applicant
Dillon Butters
Planning authority
North Yorkshire
Planning application reference
2009/0744/EIA
Appeal reference
AP/2012/0008/REF
Turbines
5
Address (REPD)
Turnham Lane, Cliffe, Selby, North Yorkshire
Council area (by location)
North Yorkshire
Time to decision
161 weeks
REPD reference
4352

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hull Road, Lundbattery storage40approved, not built0.7
Newlands Farm, Turnham Lanesolar farm49.9application submitted1.2
Osgodby Grange, Osgodby Solar Energysolar farm49.9approved, not built2.2
Barlow Road, Barlow Roadbattery storage80application withdrawn3.1
Camblesforth Solar Farmsolar farm49.9approved, not built4.7
Drax Re-Powerbattery storage200approved, not built5.2
Lakeside Energy Storage Facilitybattery storage99.9approved, not built5.2
Hales Lanebattery storage100approved, not built6.0
Carlton Solar Farmsolar farm50approved, not built6.2