Energy Projects Near You

Camblesforth Solar Farm (49.9 MW)

Camblesforth Solar Farm is a 49.9 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 8 July 2022, not yet built; the record was last updated on 7 February 2021. REPD also records that the planning permission expired on 8 July 2025, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
7 February 2021record last updated
North Yorkshirecouncil area

REPD also records that the planning permission expired on 8 July 2025, so the project may not go ahead in this form.

Planning timeline

DateStage
30 June 2021Application submitted
8 July 2022Planning permission granted
8 July 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
7 February 2021
Operator or applicant
Island Green Power UK
Planning authority
North Yorkshire
Planning application reference
2021/0788/EIA
Site area
112.7 ha
Address (REPD)
Land Off, Camela Lane, Camblesforth, Selby, North Yorkshire
Council area (by location)
North Yorkshire
Time to decision
53 weeks
REPD reference
8100

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Drax Re-Powerbattery storage200approved, not built1.7
Lakeside Energy Storage Facilitybattery storage99.9approved, not built2.1
Station Road, Carltonbattery storage99approved, not built2.5
Carlton Solar Farmsolar farm50approved, not built2.6
Hales Lanebattery storage100approved, not built2.6
Helios Renewable Energy Projectsolar farm190approved, not built4.4
Cleek Hallwind farm15abandoned4.7
Newlands Farm, Turnham Lanesolar farm49.9application submitted4.7
Barlow Road, Barlow Roadbattery storage80application withdrawn4.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7359, -1.0205).