Energy Projects Near You

Carlton Solar Farm (50 MW)

Carlton Solar Farm is a 50 MW solar farm project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 17 April 2024, not yet built; the record was last updated on 27 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

50 MWsolar farm
approved, not builtstatus in REPD
27 February 2026record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
2 February 2023Application submitted
17 April 2024Planning permission granted
17 April 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
50 MW
Status (REPD)
approved, not built
Record last updated
27 February 2026
Operator or applicant
Island Green Power
Planning authority
North Yorkshire
Planning application reference
2023/0128/EIA
Site area
166.0 ha
Address (REPD)
S/O A645 Wade House Lane Drax Selby
Council area (by location)
North Yorkshire
Time to decision
63 weeks
Contracts for Difference
AR6 & AR7a
REPD reference
12017

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Hales Lanebattery storage100approved, not built0.3
Lakeside Energy Storage Facilitybattery storage99.9approved, not built1.0
Drax Re-Powerbattery storage200approved, not built1.1
Station Road, Carltonbattery storage99approved, not built2.4
Camblesforth Solar Farmsolar farm49.9approved, not built2.6
Rusholme Wind Farmwind farm24operational2.7
Rusholme Grangebattery storage40operational3.4
Rawcliffe Estate, Bridge Lane Solar Farmsolar farm6approved, not built5.0
Helios Renewable Energy Projectsolar farm190approved, not built5.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7237, -0.9869).