Energy Projects Near You

Rusholme Grange (40 MW battery storage)

Rusholme Grange is a 40 MW battery storage project in North Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 August 2024; the record was last updated on 23 August 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
operationalstatus in REPD
23 August 2024record last updated
North Yorkshirecouncil area

Planning timeline

DateStage
26 May 2021Application submitted
3 September 2021Planning permission granted
1 January 2022Construction started
1 August 2024Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
operational
Record last updated
23 August 2024
Operator or applicant
Harmony Energy Storage
Planning authority
North Yorkshire
Planning application reference
2021/0601/FUL
Address (REPD)
Rusholme Grange, Rusholme Lane, Drax, Selby
Council area (by location)
North Yorkshire
Time to decision
14 weeks
REPD reference
9121

Earlier applications for this site

ApplicationMWSubmittedOutcome
Rusholme Grange 2017/1018/FULM3515 September 2017replaced by a revised application

Who decides

ApplicationsNorth YorkshireUK
Decided applications (solar, wind, battery)16510,236
Refused28 (17%)19%
Solar refused15 of 11212%
Onshore wind refused8 of 2445%
Battery storage refused5 of 2916%
Median time from submission to decision15.3 weeks17.0 weeks
Appeals lodged / allowed13 / 12—

Other large projects within 10 km

ProjectTypeMWStatuskm
Rusholme Wind Farmwind farm24operational0.7
Hales Lanebattery storage100approved, not built3.2
Carlton Solar Farmsolar farm50approved, not built3.4
Lakeside Energy Storage Facilitybattery storage99.9approved, not built3.4
Drax Re-Powerbattery storage200approved, not built3.8
East Yorkshire Solar Farmsolar farm400approved, not built5.0
Rawcliffe Estate, Bridge Lane Solar Farmsolar farm6approved, not built5.3
Camblesforth Solar Farmsolar farm49.9approved, not built5.5
Station Road, Carltonbattery storage99approved, not built5.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7312, -0.9374).