East Yorkshire Solar Farm (400 MW)

East Yorkshire Solar Farm is a 400 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 9 May 2025, not yet built; the record was last updated on 29 July 2025. As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010143).

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWsolar farm
approved, not builtstatus in REPD
29 July 2025record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
21 November 2023Application submitted
9 May 2025Development consent granted (Secretary of State)

Project details

Technology
solar farm
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
29 July 2025
Operator or applicant
Boom Power
Planning authority
The Planning Inspectorate - National Infrastructure
Planning application reference
EN010143
Site area
1,276.0 ha
Address (REPD)
Howden, Goole
Council area (by location)
East Riding of Yorkshire
Time to decision
76 weeks
REPD reference
11678

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Official project record at the Planning Inspectorate (EN010143)

Who decides

As a nationally significant project, it was decided by the Secretary of State for Energy Security and Net Zero on a Development Consent Order after examination by the Planning Inspectorate (EN010143). All Energy Secretary decisions on solar and wind farms. The Planning Inspectorate - National Infrastructure refused 7% of 46 decided solar, wind and battery applications in REPD (median 73 weeks to a decision). Across all UK planning authorities 19% of 10,236 decided applications were refused.

Other large projects within 10 km

ProjectTypeMWStatuskm
Sixpenny Wood Windfarmwind farm33operational3.7
Rusholme Grangebattery storage40operational5.0
Spaldington Common wind clusterwind farm5refused5.2
Rusholme Wind Farmwind farm24operational5.7
Spaldington Airfieldwind farm12.5operational6.9
River Valley Wind farmwind farm18refused7.4
Charity Farmwind farm32application withdrawn7.8
Goole Fields ll Wind Farmwind farm34.9operational7.9
Hales Lanebattery storage100approved, not built8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7469, -0.8654).