Renewable energy projects in East Riding of Yorkshire
162 solar, wind or battery projects of 150 kW or more are located in East Riding of Yorkshire (REPD, July 2026 extract): 11 pending, 97 approved but not running, 29 operational and 10 refused. The council refused 26 of 143 decided applications (18%; UK 19%), with a median 19 weeks from submission to decision.
162projects in the council area
11awaiting a decision
97approved, not running
18%of decisions refused
How East Riding of Yorkshire decides
| Applications | East Riding of Yorkshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 143 | 10,236 |
| Refused | 26 (18%) | 19% |
| Solar refused | 1 of 59 | 12% |
| Onshore wind refused | 24 of 63 | 45% |
| Battery storage refused | 1 of 21 | 16% |
| Median time from submission to decision | 18.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 4 / 10 | — |
Projects in East Riding of Yorkshire
Projects of 1 MW and more (94)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| East Yorkshire Solar Farmsolar farm | solar farm | 400 | approved, not builtupdated Jul 2025 | Nov 2023 | granted May 2025 | Jul 2025 |
| Thornton Battery Storagebattery storage | battery storage | 400 | approved, not builtupdated May 2026 | Jun 2025 | granted Feb 2026 | May 2026 |
| Peartree Hill Solar Farmsolar farm | solar farm | 320 | approved, not builtupdated Jul 2026 | Feb 2025 | granted Jul 2026 | Jul 2026 |
| Ryedale Farm, Seaton Common Lanebattery storage | battery storage | 300 | approved, not builtupdated Jan 2026 | Jun 2025 | granted Dec 2025 | Jan 2026 |
| Staithes Road, Saltend -Battery Energy Storage Systembattery storage | battery storage | 240 | approved, not builtupdated Nov 2025 | Dec 2024 | granted Jul 2025 | Nov 2025 |
| Soay Solar Farm and Greener Grid Parkbattery storage | battery storage | 200 | under constructionupdated Mar 2026 | Jan 2022 | granted Nov 2022 | Mar 2026 |
| Kingston International Business Parkbattery storage | battery storage | 200 | approved, not builtupdated Nov 2025 | Oct 2024 | granted Jul 2025 | Nov 2025 |
| Tara Melbourne Road, Thorntonbattery storage | battery storage | 200 | approved, not builtupdated Nov 2025 | Apr 2025 | granted Aug 2025 | Nov 2025 |
| Soay Solar Farm and Greener Grid Parksolar farm | solar farm | 50 | under constructionupdated Mar 2026 | Jan 2022 | granted Nov 2022 | Mar 2026 |
| Creyke Beckbattery storage | battery storage | 49.9 | operationalupdated Jan 2019 | Apr 2017 | granted Jun 2017 | Jan 2019 |
| Creyke Beck Substation Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Feb 2024 | Aug 2021 | granted Jan 2022 | Feb 2024 |
| Turf Carr Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Jun 2024 | Sep 2022 | granted May 2024 | Jun 2024 |
| Kenley Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Feb 2025 | May 2022 | granted Nov 2022 | Feb 2025 |
| Carr Lane, Tickton Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Aug 2025 | Dec 2022 | granted Jul 2025 | Aug 2025 |
| Sunderlandwick Solar Farmsolar farm | solar farm | 49.9 | approved, not built may be out of dateupdated Feb 2026 | Aug 2022 | granted Apr 2023 | Feb 2026 |
| Scurf Dyke Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Nov 2022 | Jan 2020 | granted Mar 2020 | Nov 2022 |
| Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagesolar farm | solar farm | 49.9 | approved, not builtupdated Nov 2024 | Mar 2023 | granted Nov 2024 | Nov 2024 |
| Kenley House Farm, Ferry Road Solar Farmsolar farm | solar farm | 49.9 | application submittedupdated Sep 2025 | Aug 2025 | — | Sep 2025 |
| Carr House Farm, Drove Lanesolar farm | solar farm | 49.9 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 |
| Neat Marsh North, Neat Marsh Road Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Jun 2026 | Jul 2025 | granted Feb 2026 | Jun 2026 |
| Pillswood Phase 1battery storage | battery storage | 49.5 | operationalupdated Nov 2022 | Apr 2017 | granted Oct 2018 | Nov 2022 |
| Pillswood Phase 2battery storage | battery storage | 49.5 | operationalupdated Nov 2022 | May 2019 | granted Jul 2023 | Nov 2022 |
| Salt End Lanebattery storage | battery storage | 49 | permission expiredupdated Jul 2020 | Nov 2017 | granted Feb 2018 | Jul 2020 |
| Aire & Calder Wind Farmwind farm | wind farm | 45 | application withdrawnupdated Jun 2011 | Aug 2005 | — | Jun 2011 |
| Back Lane, Skerne Solar Farm & Battery Storagesolar farm | solar farm | 45 | approved, not built may be out of dateupdated Nov 2022 | Jul 2020 | granted Oct 2020 | Nov 2022 |
| Harbour Farm Solar Farmsolar farm | solar farm | 42 | application submittedupdated Oct 2025 | Sep 2025 | — | Oct 2025 |
| Field House Solar Farmsolar farm | solar farm | 40 | approved, not built may be out of dateupdated Jul 2022 | Mar 2022 | granted Jul 2022 | Jul 2022 |
| Field House Solar Farmbattery storage | battery storage | 40 | approved, not built may be out of dateupdated Apr 2022 | Mar 2022 | granted Jul 2022 | Apr 2022 |
| Old Chalk Pit, West Back Side - Three Oaks Renewable Parksolar farm | solar farm | 39 | approved, not builtupdated Feb 2026 | Oct 2022 | granted Mar 2024 | Feb 2026 |
| Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farmsolar farm | solar farm | 35 | approved, not builtupdated Mar 2026 | Jun 2024 | granted Jan 2026 | Mar 2026 |
| Goole Fields ll Wind Farmwind farm | wind farm | 34.9 | operationalupdated Mar 2017 | Jan 2012 | granted May 2014 | Mar 2017 |
| Sixpenny Wood Windfarmwind farm | wind farm | 33 | operationalupdated Jan 2015 | Jul 2007 | granted Dec 2009 | Jan 2015 |
| Goole Fieldswind farm | wind farm | 32.8 | operationalupdated Aug 2014 | Apr 2003 | granted Sep 2003 | Aug 2014 |
| Charity Farmwind farm | wind farm | 32 | application withdrawnupdated Mar 2011 | Aug 2009 | — | Mar 2011 |
| Lissett Airfield Wind Farmwind farm | wind farm | 30 | operationalupdated Jun 2010 | Jul 2006 | granted Feb 2007 | Jun 2010 |
| Back Lane, Skerne Solar Farm & Battery Storagebattery storage | battery storage | 30 | approved, not built may be out of dateupdated Nov 2022 | Jul 2020 | granted Oct 2020 | Nov 2022 |
| Market Weighton Road, Barlby Solar Farm & Battery Storagesolar farm | solar farm | 30 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 |
| Humberfield Recycling Centrebattery storage | battery storage | 30 | approved, not builtupdated Nov 2025 | May 2025 | granted Jul 2025 | Nov 2025 |
| Fraisthorpe Wind Farmwind farm | wind farm | 29.7 | operationalupdated Oct 2016 | Feb 2012 | granted Jan 2013 | Oct 2016 |
| Hull Solar Farmsolar farm | solar farm | 25.7 | under constructionupdated Jan 2020 | Jun 2015 | granted Oct 2015 | Jan 2020 |
| Withernwick (withdrawn)wind farm | wind farm | 25 | application withdrawnupdated Jun 2010 | Apr 2007 | — | Jun 2010 |
| High Wood Wind Farmwind farm | wind farm | 25 | application withdrawnupdated Sep 2015 | Feb 2015 | — | Sep 2015 |
| Hall Farm Routhwind farm | wind farm | 24.6 | operationalupdated Nov 2013 | Oct 2006 | granted Feb 2009 | Nov 2013 |
| Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagebattery storage | battery storage | 20 | approved, not builtupdated Nov 2024 | Mar 2023 | granted Nov 2024 | Nov 2024 |
| Withernwickwind farm | wind farm | 18 | operationalupdated Jun 2013 | Apr 2008 | granted Sep 2008 | Jun 2013 |
| River Valley Wind farmwind farm | wind farm | 18 | refusedupdated Nov 2014 | Nov 2012 | refused Aug 2013 | Nov 2014 |
| Roos Wind Farm (Resubmission)wind farm | wind farm | 17.1 | operationalupdated Jun 2013 | Jan 2009 | granted May 2010 | Jun 2013 |
| Bonwickwind farm | wind farm | 17 | refusedupdated Mar 2017 | Mar 2015 | refused Feb 2017 | Mar 2017 |
| Sober Hill Wind Farmwind farm | wind farm | 15 | operationalupdated Aug 2014 | Oct 2008 | granted Mar 2010 | Aug 2014 |
| Spaldington Airfieldwind farm | wind farm | 12.5 | operationalupdated May 2016 | Nov 2009 | granted Sep 2011 | May 2016 |
| Lissett Airfield Wind Farm Extensionwind farm | wind farm | 12.5 | appeal withdrawnupdated Jan 2016 | Oct 2013 | refused Aug 2015 | Jan 2016 |
| Thornholme Wind Farmwind farm | wind farm | 12 | refused on appealupdated Jun 2014 | Sep 2011 | refused Dec 2012 | Jun 2014 |
| Skeffling Wind Farmwind farm | wind farm | 11.5 | application withdrawnupdated May 2015 | Jan 2012 | — | May 2015 |
| Eastfield Farm Wind Farmwind farm | wind farm | 11.4 | refusedupdated Aug 2005 | Sep 1998 | refused Sep 2000 | Aug 2005 |
| Burton Pidsea (Wadworth Hill) Wind Farmwind farm | wind farm | 10.2 | operationalupdated Jan 2014 | May 2008 | granted Sep 2009 | Jan 2014 |
| Sancton Hillwind farm | wind farm | 10 | operationalupdated Dec 2013 | May 2010 | granted Feb 2011 | Dec 2013 |
| Rawcliffe Bridge Wind Farmwind farm | wind farm | 10 | refusedupdated Apr 2015 | Feb 2014 | refused Feb 2015 | Apr 2015 |
| Market Weighton Road, Barlby Solar Farm & Battery Storagebattery storage | battery storage | 10 | application submittedupdated Oct 2025 | Jul 2025 | — | Oct 2025 |
| Croxby Hall Farm, Inglemire Lane Solar Farm & Battery Storagesolar farm | solar farm | 9.7 | application withdrawnupdated Mar 2024 | Aug 2023 | — | Mar 2024 |
| Snuff Mill Lane Gates Solar Farm & Battery Storagesolar farm | solar farm | 9.7 | application withdrawnupdated Mar 2024 | Aug 2023 | — | Mar 2024 |
| Out Newton Wind Farmwind farm | wind farm | 9 | operationalupdated Apr 2009 | Nov 1998 | granted Sep 2000 | Apr 2009 |
| Withernwick extensionwind farm | wind farm | 8.2 | operationalupdated Nov 2019 | Jun 2014 | granted Dec 2016 | Nov 2019 |
| Land South Of Demming Farmwind farm | wind farm | 8 | refusedupdated Aug 2014 | Mar 2013 | refused Jan 2014 | Aug 2014 |
| Tedder Hill Wind clusterwind farm | wind farm | 7.5 | operationalupdated Mar 2014 | May 2006 | granted Jan 2010 | Mar 2014 |
| Far Marsh Farmwind farm | wind farm | 7.5 | operationalupdated Mar 2017 | Dec 2012 | granted Dec 2013 | Mar 2017 |
| Monkwith Wind Farmwind farm | wind farm | 6.9 | refused on appealupdated Dec 2011 | Jun 2009 | refused Jan 2010 | Dec 2011 |
| Rotsea Wind Farmwind farm | wind farm | 6.9 | refusedupdated Dec 2015 | Nov 2013 | refused Nov 2015 | Dec 2015 |
| Bagletts Wind Farmwind farm | wind farm | 6.9 | application withdrawnupdated Aug 2015 | Dec 2014 | — | Aug 2015 |
| Carnabywind farm | wind farm | 6 | approved, not built may be out of dateupdated Jan 2020 | Nov 2010 | granted Feb 2012 | Jan 2020 |
| Rawcliffe Estate, Bridge Lane Solar Farmsolar farm | solar farm | 6 | approved, not builtupdated Jan 2025 | Aug 2024 | granted Dec 2024 | Jan 2025 |
| Redhall Industrial Estatesolar farm | solar farm | 5 | operationalupdated Feb 2015 | Oct 2012 | granted Jan 2013 | Feb 2015 |
| Melton Common Wind Clusterwind farm | wind farm | 5 | operationalupdated Sep 2023 | Jun 2013 | granted Dec 2013 | Sep 2023 |
| Spaldington Common wind clusterwind farm | wind farm | 5 | refusedupdated Sep 2013 | Apr 2013 | refused Sep 2013 | Sep 2013 |
| Melton Waste Parkwind farm | wind farm | 5 | operationalupdated Jun 2017 | Feb 2015 | granted Apr 2015 | Jun 2017 |
| Land at Pollington Airfieldsolar farm | solar farm | 5 | operationalupdated Feb 2016 | May 2015 | granted Jul 2015 | Feb 2016 |
| Cottingham Solar Farmsolar farm | solar farm | 5 | operationalupdated May 2022 | Jun 2021 | granted Mar 2022 | May 2022 |
| Wienerberger Limited, Tongue Lanesolar farm | solar farm | 4.7 | application withdrawnupdated Jun 2025 | May 2025 | — | Jun 2025 |
| Melton Common Wind Clusterwind farm | wind farm | 4.6 | application submitted may be out of dateupdated Sep 2023 | Aug 2023 | — | Sep 2023 |
| Skipsea Lane, Dunnington Wind Farmwind turbine | wind turbine | 4.2 | approved, not built may be out of dateupdated Mar 2022 | Mar 2022 | granted Oct 2022 | Mar 2022 |
| Croda Chemicals Europewind turbine | wind turbine | 3 | operationalupdated Dec 2009 | Apr 2006 | granted Oct 2006 | Dec 2009 |
| Meltonwind farm | wind farm | 3 | approved, not builtupdated Jan 2025 | May 2022 | granted Feb 2024 | Jan 2025 |
| Howdens Joinery, Thorpe Roadrooftop solar | rooftop solar | 3 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Mar 2024 | Apr 2024 |
| Normandy Barrackssolar farm | solar farm | 2.3 | under constructionupdated Apr 2021 | — | — | Apr 2021 |
| Melton Common Wind Clusterwind turbine | wind turbine | 2.3 | approved, not built may be out of dateupdated Sep 2023 | Jun 2014 | granted Feb 2016 | Sep 2023 |
| Celcon Blocks Ltdwind turbine | wind turbine | 2 | operationalupdated Feb 2017 | Aug 2009 | granted Oct 2012 | Feb 2017 |
| Outstray Farm Wind Projectwind farm | wind farm | 1.8 | application withdrawnupdated Aug 2005 | Jun 1999 | — | Aug 2005 |
| Gallymoor Landfill Sitewind farm | wind farm | 1.8 | approved, not built may be out of dateupdated Jan 2020 | Feb 2011 | granted Jul 2012 | Jan 2020 |
| The Limes Wind Turbineswind farm | wind farm | 1.7 | operationalupdated Jul 2018 | May 2011 | granted Nov 2012 | Jul 2018 |
| Bayram Timber Limited, Gibson Lane Southrooftop solar | rooftop solar | 1.7 | approved, not builtupdated May 2026 | Feb 2026 | granted Apr 2026 | May 2026 |
| Yorkshire Grown Produce, Main Roadrooftop solar | rooftop solar | 1.5 | approved, not builtupdated Mar 2024 | Jan 2024 | granted Feb 2024 | Mar 2024 |
| Newton Farm, Tongue Lane Solar Farm & Battery Storagesolar farm | solar farm | 1.5 | approved, not builtupdated Jul 2025 | Dec 2024 | granted Jun 2025 | Jul 2025 |
| Saltend Wind Turbinewind turbine | wind turbine | 1.3 | operationalupdated Jun 2010 | Dec 2005 | granted Mar 2006 | Jun 2010 |
| Bowmar Carr Road, Burton Pidseasolar farm | solar farm | 1 | approved, not built may be out of dateupdated Jun 2022 | Jun 2022 | granted Oct 2022 | Jun 2022 |
| Wind Turbine at North Farm Wind Turbines Thorpe Le Street Road Thorpe Le Streetwind turbine | wind turbine | 1 | approved, not builtupdated Feb 2024 | Dec 2022 | granted Feb 2024 | Feb 2024 |
Smaller schemes under 1 MW, mostly rooftop solar (60)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Robinson Contract Services, Catfoss Industrial Estatesolar farm | solar farm | 1 | approved, not builtupdated Aug 2024 | May 2024 | granted Jul 2024 | Aug 2024 |
| E B Bradshaw And Sons, Bell Millssolar farm | solar farm | 0.8 | approved, not builtupdated Jun 2025 | Mar 2025 | granted Jun 2025 | Jun 2025 |
| Church Hill Farm, Church Hillsolar farm | solar farm | 0.8 | approved, not builtupdated Feb 2024 | Oct 2023 | granted Jan 2024 | Feb 2024 |
| Burton Fleming Grange, Wold Newton Roadwind turbine | wind turbine | 0.7 | approved, not builtupdated Sep 2023 | Apr 2023 | granted Aug 2023 | Sep 2023 |
| Wingfield Wayrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Feb 2022 | Feb 2022 | granted Mar 2022 | Feb 2022 |
| Tesco Distribution Centre. Tom Pudding Wayrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2025 | Jun 2025 | granted Jul 2025 | Nov 2025 |
| Springdale Farm, High Streetrooftop solar | rooftop solar | 0.5 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 |
| Raven Hill Farm, Langtoft Roadwind farm | wind farm | 0.5 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 |
| Low Cowlam Farm, Driffield Roadwind farm | wind farm | 0.5 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 |
| Great Kendale, Naffertonwind turbine | wind turbine | 0.5 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Jan 2026 | Mar 2026 |
| Grove Farm, Main Streetwind farm | wind farm | 0.5 | approved, not builtupdated Nov 2025 | Apr 2025 | granted Oct 2025 | Nov 2025 |
| Middledale Heights, Langtoft Roadwind farm | wind farm | 0.5 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 |
| Dalton Gates Farm, North Dalton Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Nov 2022 | Sep 2022 | granted Nov 2022 | Nov 2022 |
| Bridlington And District Hospital, Bessingby Road Battery Unitbattery storage | battery storage | 0.4 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 |
| Thornwick Bay Holiday Village, North Marine Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 |
| Victory Conversions, Sandholme Business Parkrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Oct 2024 | Jul 2024 | granted Sep 2024 | Oct 2024 |
| South Shore Holiday Villagesolar farm | solar farm | 0.4 | operationalupdated Mar 2023 | Jun 2019 | granted Dec 2020 | Mar 2023 |
| Country Style Foods, Carnaby Industrial Estaterooftop solar | rooftop solar | 0.4 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Aug 2023 | Sep 2023 |
| Rasher House, Catfoss Lanesolar farm | solar farm | 0.4 | approved, not builtupdated Jul 2026 | Apr 2026 | granted Jun 2026 | Jul 2026 |
| Luxinar Limited, Rofin Houserooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2023 | Feb 2023 | granted Apr 2023 | May 2023 |
| Modular & Portable Buildings Hire Limited, Brandesburtonrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 |
| Bessingby Roadsolar farm | solar farm | 0.4 | application submitted may be out of dateupdated May 2022 | Apr 2022 | — | May 2022 |
| Cottingham Water Pumping Station, Mill Housesolar farm | solar farm | 0.4 | approved, not builtupdated Oct 2023 | Jun 2023 | granted Sep 2023 | Oct 2023 |
| Grange Farm, Finchcroft Lanesolar farm | solar farm | 0.4 | approved, not built may be out of dateupdated Aug 2023 | Apr 2023 | granted Jun 2023 | Aug 2023 |
| Commons Farm, Thorne Roadsolar farm | solar farm | 0.4 | approved, not built may be out of dateupdated Aug 2023 | Jun 2023 | granted Jul 2023 | Aug 2023 |
| Braffords Farm, Riplingham Roadwind turbine | wind turbine | 0.3 | approved, not builtupdated Aug 2024 | Dec 2023 | granted Jul 2024 | Aug 2024 |
| Newland Farm, Station Roadrooftop solar | rooftop solar | 0.3 | application submittedupdated Sep 2024 | Aug 2024 | — | Sep 2024 |
| The Gardenssolar farm | solar farm | 0.3 | permission expiredupdated Mar 2020 | Dec 2019 | granted Nov 2020 | Mar 2020 |
| St Helens Farm, Reangamoor Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 |
| Ryedale Farm, Seaton Common Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Aug 2025 | Jul 2025 | granted Aug 2025 | Aug 2025 |
| Withernsea High School, Hull Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 |
| A B Graphic International Limited , Wadsworth Roadrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated May 2023 | May 2023 | granted Jul 2023 | May 2023 |
| Croda Europe, Tom Pudding Waysolar farm | solar farm | 0.3 | approved, not builtupdated Oct 2023 | Jun 2023 | granted Oct 2023 | Oct 2023 |
| Spire Hospital, Lowfield Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2024 | Mar 2024 | granted Apr 2024 | May 2024 |
| Greenlands Farm, Barmby Moor Solar Photovoltaic Arraysrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 |
| Cold Harbour Farm, Cold Harbour Roadsolar farm | solar farm | 0.3 | approved, not builtupdated May 2024 | Dec 2023 | granted Apr 2024 | May 2024 |
| Sand Le Mere Holiday Village, Southfield Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2026 | Dec 2025 | granted Jan 2026 | Feb 2026 |
| Melton Enterprise Park, Redcliff Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Feb 2026 | Apr 2026 |
| Towthorpe Manor Farm, Towthorpe Roadwind turbine | wind turbine | 0.2 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 |
| Market Weighton Road, Middleton On The Wolds -Wind Turbinewind turbine | wind turbine | 0.2 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Dec 2025 | Jan 2026 |
| Weighton Wold, Arras Hillwind turbine | wind turbine | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 |
| Cowden Magna Farm, Cowdenwind turbine | wind turbine | 0.2 | approved, not builtupdated Jan 2026 | Nov 2025 | granted Jan 2026 | Jan 2026 |
| Burton Roadwind turbine | wind turbine | 0.2 | approved, not builtupdated Jan 2026 | Nov 2025 | granted Jan 2026 | Jan 2026 |
| Burton Road, Burton Pidseawind turbine | wind turbine | 0.2 | approved, not builtupdated May 2026 | Jan 2026 | granted Mar 2026 | May 2026 |
| Priest Close, Burton Roadwind turbine | wind turbine | 0.2 | approved, not builtupdated May 2026 | Feb 2026 | granted Mar 2026 | May 2026 |
| Bessingby Roadrooftop solar | rooftop solar | 0.2 | application submitted may be out of dateupdated May 2022 | Apr 2022 | — | May 2022 |
| Little Pockthorpe Farm, Pockthorpe Lanewind farm | wind farm | 0.2 | approved, not builtupdated Nov 2025 | Apr 2025 | granted Jul 2025 | Nov 2025 |
| Tuft Hill Farm, Woldgatewind turbine | wind turbine | 0.2 | approved, not builtupdated Nov 2025 | Jun 2025 | granted Aug 2025 | Nov 2025 |
| Weighton Road, Sanctonwind turbine | wind turbine | 0.2 | approved, not builtupdated Jan 2026 | Nov 2025 | granted Dec 2025 | Jan 2026 |
| Southfield House Farm, Hornsea Roadwind turbine | wind turbine | 0.2 | application submittedupdated Feb 2026 | Jan 2026 | — | Feb 2026 |
| North Fordon Farm, Danebury Manor Roadwind turbine | wind turbine | 0.2 | application submitted | May 2026 | — | — |
| Far Grange Caravan Park, Hornsea Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Mar 2023 | granted Apr 2023 | Jul 2023 |
| The Oaks Golf Clubsolar farm | solar farm | 0.2 | approved, not built may be out of dateupdated Feb 2022 | Jan 2022 | granted Nov 2022 | Feb 2022 |
| Wigwam Holidays Ball Hall Farm, Ballhall Lanesolar farm | solar farm | 0.2 | application submittedupdated May 2026 | Apr 2026 | — | May 2026 |
| B W Industries Limited, Carnaby Industrial Estaterooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2025 | Sep 2024 | granted Nov 2024 | Jan 2025 |
| Ferndale Park Newfields Industrial Estatebattery storage | battery storage | — | refusedupdated Nov 2018 | Oct 2017 | refused Jul 2018 | Nov 2018 |
| Scurf Dyke Solar Farmbattery storage | battery storage | — | approved, not builtupdated Oct 2022 | Jan 2020 | granted Mar 2020 | Oct 2022 |
| Old Chalk Pit, West Back Side - Three Oaks Renewable Parkbattery storage | battery storage | — | approved, not builtupdated Feb 2026 | Oct 2022 | granted Mar 2024 | Feb 2026 |
| Ab Graphic International, Carnaby Industrial Estaterooftop solar | rooftop solar | — | approved, not builtupdated Apr 2023 | Dec 2022 | granted Jan 2023 | Apr 2023 |
| Bridlington Waste Water Treatment Workssolar farm | solar farm | — | approved, not builtupdated Sep 2023 | Jun 2023 | granted Aug 2023 | Sep 2023 |
8 more projects not listed (furthest or smallest).
Postcode districts in East Riding of Yorkshire
| District | Projects within 10 km | Pending | Approved | Operational |
|---|---|---|---|---|
| DN14 | 35 | 3 | 18 | 10 |
| HU10 | 50 | 3 | 35 | 8 |
| HU11 | 42 | 2 | 30 | 5 |
| HU12 | 26 | 2 | 13 | 7 |
| HU13 | 47 | 2 | 32 | 8 |
| HU14 | 32 | 1 | 19 | 6 |
| HU15 | 17 | 1 | 10 | 3 |
| HU16 | 55 | 2 | 40 | 7 |
| HU17 | 36 | 1 | 24 | 6 |
| HU18 | 11 | 1 | 6 | 2 |
| HU19 | 12 | 0 | 4 | 4 |
| HU20 | 29 | 1 | 15 | 8 |
| YO15 | 16 | 2 | 10 | 2 |
| YO16 | 20 | 2 | 14 | 2 |
| YO25 | 17 | 0 | 14 | 1 |
| YO41 | 22 | 1 | 19 | 1 |
| YO42 | 17 | 3 | 12 | 0 |
| YO43 | 13 | 2 | 7 | 3 |
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to East Riding of Yorkshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.