Renewable energy projects in East Riding of Yorkshire

162 solar, wind or battery projects of 150 kW or more are located in East Riding of Yorkshire (REPD, July 2026 extract): 11 pending, 97 approved but not running, 29 operational and 10 refused. The council refused 26 of 143 decided applications (18%; UK 19%), with a median 19 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

162projects in the council area
11awaiting a decision
97approved, not running
18%of decisions refused

How East Riding of Yorkshire decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Projects in East Riding of Yorkshire

Projects of 1 MW and more (94)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
East Yorkshire Solar Farmsolar farmsolar farm400approved, not builtupdated Jul 2025Nov 2023granted May 2025Jul 2025
Thornton Battery Storagebattery storagebattery storage400approved, not builtupdated May 2026Jun 2025granted Feb 2026May 2026
Peartree Hill Solar Farmsolar farmsolar farm320approved, not builtupdated Jul 2026Feb 2025granted Jul 2026Jul 2026
Ryedale Farm, Seaton Common Lanebattery storagebattery storage300approved, not builtupdated Jan 2026Jun 2025granted Dec 2025Jan 2026
Staithes Road, Saltend -Battery Energy Storage Systembattery storagebattery storage240approved, not builtupdated Nov 2025Dec 2024granted Jul 2025Nov 2025
Soay Solar Farm and Greener Grid Parkbattery storagebattery storage200under constructionupdated Mar 2026Jan 2022granted Nov 2022Mar 2026
Kingston International Business Parkbattery storagebattery storage200approved, not builtupdated Nov 2025Oct 2024granted Jul 2025Nov 2025
Tara Melbourne Road, Thorntonbattery storagebattery storage200approved, not builtupdated Nov 2025Apr 2025granted Aug 2025Nov 2025
Soay Solar Farm and Greener Grid Parksolar farmsolar farm50under constructionupdated Mar 2026Jan 2022granted Nov 2022Mar 2026
Creyke Beckbattery storagebattery storage49.9operationalupdated Jan 2019Apr 2017granted Jun 2017Jan 2019
Creyke Beck Substation Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2024Aug 2021granted Jan 2022Feb 2024
Turf Carr Solar Farmsolar farmsolar farm49.9approved, not builtupdated Jun 2024Sep 2022granted May 2024Jun 2024
Kenley Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2025May 2022granted Nov 2022Feb 2025
Carr Lane, Tickton Solar Farmsolar farmsolar farm49.9approved, not builtupdated Aug 2025Dec 2022granted Jul 2025Aug 2025
Sunderlandwick Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Feb 2026Aug 2022granted Apr 2023Feb 2026
Scurf Dyke Solar Farmsolar farmsolar farm49.9approved, not builtupdated Nov 2022Jan 2020granted Mar 2020Nov 2022
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagesolar farmsolar farm49.9approved, not builtupdated Nov 2024Mar 2023granted Nov 2024Nov 2024
Kenley House Farm, Ferry Road Solar Farmsolar farmsolar farm49.9application submittedupdated Sep 2025Aug 2025—Sep 2025
Carr House Farm, Drove Lanesolar farmsolar farm49.9approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023
Neat Marsh North, Neat Marsh Road Solar Farmsolar farmsolar farm49.9approved, not builtupdated Jun 2026Jul 2025granted Feb 2026Jun 2026
Pillswood Phase 1battery storagebattery storage49.5operationalupdated Nov 2022Apr 2017granted Oct 2018Nov 2022
Pillswood Phase 2battery storagebattery storage49.5operationalupdated Nov 2022May 2019granted Jul 2023Nov 2022
Salt End Lanebattery storagebattery storage49permission expiredupdated Jul 2020Nov 2017granted Feb 2018Jul 2020
Aire & Calder Wind Farmwind farmwind farm45application withdrawnupdated Jun 2011Aug 2005—Jun 2011
Back Lane, Skerne Solar Farm & Battery Storagesolar farmsolar farm45approved, not built may be out of dateupdated Nov 2022Jul 2020granted Oct 2020Nov 2022
Harbour Farm Solar Farmsolar farmsolar farm42application submittedupdated Oct 2025Sep 2025—Oct 2025
Field House Solar Farmsolar farmsolar farm40approved, not built may be out of dateupdated Jul 2022Mar 2022granted Jul 2022Jul 2022
Field House Solar Farmbattery storagebattery storage40approved, not built may be out of dateupdated Apr 2022Mar 2022granted Jul 2022Apr 2022
Old Chalk Pit, West Back Side - Three Oaks Renewable Parksolar farmsolar farm39approved, not builtupdated Feb 2026Oct 2022granted Mar 2024Feb 2026
Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farmsolar farmsolar farm35approved, not builtupdated Mar 2026Jun 2024granted Jan 2026Mar 2026
Goole Fields ll Wind Farmwind farmwind farm34.9operationalupdated Mar 2017Jan 2012granted May 2014Mar 2017
Sixpenny Wood Windfarmwind farmwind farm33operationalupdated Jan 2015Jul 2007granted Dec 2009Jan 2015
Goole Fieldswind farmwind farm32.8operationalupdated Aug 2014Apr 2003granted Sep 2003Aug 2014
Charity Farmwind farmwind farm32application withdrawnupdated Mar 2011Aug 2009—Mar 2011
Lissett Airfield Wind Farmwind farmwind farm30operationalupdated Jun 2010Jul 2006granted Feb 2007Jun 2010
Back Lane, Skerne Solar Farm & Battery Storagebattery storagebattery storage30approved, not built may be out of dateupdated Nov 2022Jul 2020granted Oct 2020Nov 2022
Market Weighton Road, Barlby Solar Farm & Battery Storagesolar farmsolar farm30application submittedupdated Oct 2025Jul 2025—Oct 2025
Humberfield Recycling Centrebattery storagebattery storage30approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025
Fraisthorpe Wind Farmwind farmwind farm29.7operationalupdated Oct 2016Feb 2012granted Jan 2013Oct 2016
Hull Solar Farmsolar farmsolar farm25.7under constructionupdated Jan 2020Jun 2015granted Oct 2015Jan 2020
Withernwick (withdrawn)wind farmwind farm25application withdrawnupdated Jun 2010Apr 2007—Jun 2010
High Wood Wind Farmwind farmwind farm25application withdrawnupdated Sep 2015Feb 2015—Sep 2015
Hall Farm Routhwind farmwind farm24.6operationalupdated Nov 2013Oct 2006granted Feb 2009Nov 2013
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagebattery storagebattery storage20approved, not builtupdated Nov 2024Mar 2023granted Nov 2024Nov 2024
Withernwickwind farmwind farm18operationalupdated Jun 2013Apr 2008granted Sep 2008Jun 2013
River Valley Wind farmwind farmwind farm18refusedupdated Nov 2014Nov 2012refused Aug 2013Nov 2014
Roos Wind Farm (Resubmission)wind farmwind farm17.1operationalupdated Jun 2013Jan 2009granted May 2010Jun 2013
Bonwickwind farmwind farm17refusedupdated Mar 2017Mar 2015refused Feb 2017Mar 2017
Sober Hill Wind Farmwind farmwind farm15operationalupdated Aug 2014Oct 2008granted Mar 2010Aug 2014
Spaldington Airfieldwind farmwind farm12.5operationalupdated May 2016Nov 2009granted Sep 2011May 2016
Lissett Airfield Wind Farm Extensionwind farmwind farm12.5appeal withdrawnupdated Jan 2016Oct 2013refused Aug 2015Jan 2016
Thornholme Wind Farmwind farmwind farm12refused on appealupdated Jun 2014Sep 2011refused Dec 2012Jun 2014
Skeffling Wind Farmwind farmwind farm11.5application withdrawnupdated May 2015Jan 2012—May 2015
Eastfield Farm Wind Farmwind farmwind farm11.4refusedupdated Aug 2005Sep 1998refused Sep 2000Aug 2005
Burton Pidsea (Wadworth Hill) Wind Farmwind farmwind farm10.2operationalupdated Jan 2014May 2008granted Sep 2009Jan 2014
Sancton Hillwind farmwind farm10operationalupdated Dec 2013May 2010granted Feb 2011Dec 2013
Rawcliffe Bridge Wind Farmwind farmwind farm10refusedupdated Apr 2015Feb 2014refused Feb 2015Apr 2015
Market Weighton Road, Barlby Solar Farm & Battery Storagebattery storagebattery storage10application submittedupdated Oct 2025Jul 2025—Oct 2025
Croxby Hall Farm, Inglemire Lane Solar Farm & Battery Storagesolar farmsolar farm9.7application withdrawnupdated Mar 2024Aug 2023—Mar 2024
Snuff Mill Lane Gates Solar Farm & Battery Storagesolar farmsolar farm9.7application withdrawnupdated Mar 2024Aug 2023—Mar 2024
Out Newton Wind Farmwind farmwind farm9operationalupdated Apr 2009Nov 1998granted Sep 2000Apr 2009
Withernwick extensionwind farmwind farm8.2operationalupdated Nov 2019Jun 2014granted Dec 2016Nov 2019
Land South Of Demming Farmwind farmwind farm8refusedupdated Aug 2014Mar 2013refused Jan 2014Aug 2014
Tedder Hill Wind clusterwind farmwind farm7.5operationalupdated Mar 2014May 2006granted Jan 2010Mar 2014
Far Marsh Farmwind farmwind farm7.5operationalupdated Mar 2017Dec 2012granted Dec 2013Mar 2017
Monkwith Wind Farmwind farmwind farm6.9refused on appealupdated Dec 2011Jun 2009refused Jan 2010Dec 2011
Rotsea Wind Farmwind farmwind farm6.9refusedupdated Dec 2015Nov 2013refused Nov 2015Dec 2015
Bagletts Wind Farmwind farmwind farm6.9application withdrawnupdated Aug 2015Dec 2014—Aug 2015
Carnabywind farmwind farm6approved, not built may be out of dateupdated Jan 2020Nov 2010granted Feb 2012Jan 2020
Rawcliffe Estate, Bridge Lane Solar Farmsolar farmsolar farm6approved, not builtupdated Jan 2025Aug 2024granted Dec 2024Jan 2025
Redhall Industrial Estatesolar farmsolar farm5operationalupdated Feb 2015Oct 2012granted Jan 2013Feb 2015
Melton Common Wind Clusterwind farmwind farm5operationalupdated Sep 2023Jun 2013granted Dec 2013Sep 2023
Spaldington Common wind clusterwind farmwind farm5refusedupdated Sep 2013Apr 2013refused Sep 2013Sep 2013
Melton Waste Parkwind farmwind farm5operationalupdated Jun 2017Feb 2015granted Apr 2015Jun 2017
Land at Pollington Airfieldsolar farmsolar farm5operationalupdated Feb 2016May 2015granted Jul 2015Feb 2016
Cottingham Solar Farmsolar farmsolar farm5operationalupdated May 2022Jun 2021granted Mar 2022May 2022
Wienerberger Limited, Tongue Lanesolar farmsolar farm4.7application withdrawnupdated Jun 2025May 2025—Jun 2025
Melton Common Wind Clusterwind farmwind farm4.6application submitted may be out of dateupdated Sep 2023Aug 2023—Sep 2023
Skipsea Lane, Dunnington Wind Farmwind turbinewind turbine4.2approved, not built may be out of dateupdated Mar 2022Mar 2022granted Oct 2022Mar 2022
Croda Chemicals Europewind turbinewind turbine3operationalupdated Dec 2009Apr 2006granted Oct 2006Dec 2009
Meltonwind farmwind farm3approved, not builtupdated Jan 2025May 2022granted Feb 2024Jan 2025
Howdens Joinery, Thorpe Roadrooftop solarrooftop solar3approved, not builtupdated Apr 2024Jan 2024granted Mar 2024Apr 2024
Normandy Barrackssolar farmsolar farm2.3under constructionupdated Apr 2021——Apr 2021
Melton Common Wind Clusterwind turbinewind turbine2.3approved, not built may be out of dateupdated Sep 2023Jun 2014granted Feb 2016Sep 2023
Celcon Blocks Ltdwind turbinewind turbine2operationalupdated Feb 2017Aug 2009granted Oct 2012Feb 2017
Outstray Farm Wind Projectwind farmwind farm1.8application withdrawnupdated Aug 2005Jun 1999—Aug 2005
Gallymoor Landfill Sitewind farmwind farm1.8approved, not built may be out of dateupdated Jan 2020Feb 2011granted Jul 2012Jan 2020
The Limes Wind Turbineswind farmwind farm1.7operationalupdated Jul 2018May 2011granted Nov 2012Jul 2018
Bayram Timber Limited, Gibson Lane Southrooftop solarrooftop solar1.7approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026
Yorkshire Grown Produce, Main Roadrooftop solarrooftop solar1.5approved, not builtupdated Mar 2024Jan 2024granted Feb 2024Mar 2024
Newton Farm, Tongue Lane Solar Farm & Battery Storagesolar farmsolar farm1.5approved, not builtupdated Jul 2025Dec 2024granted Jun 2025Jul 2025
Saltend Wind Turbinewind turbinewind turbine1.3operationalupdated Jun 2010Dec 2005granted Mar 2006Jun 2010
Bowmar Carr Road, Burton Pidseasolar farmsolar farm1approved, not built may be out of dateupdated Jun 2022Jun 2022granted Oct 2022Jun 2022
Wind Turbine at North Farm Wind Turbines Thorpe Le Street Road Thorpe Le Streetwind turbinewind turbine1approved, not builtupdated Feb 2024Dec 2022granted Feb 2024Feb 2024
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Robinson Contract Services, Catfoss Industrial Estatesolar farmsolar farm1approved, not builtupdated Aug 2024May 2024granted Jul 2024Aug 2024
E B Bradshaw And Sons, Bell Millssolar farmsolar farm0.8approved, not builtupdated Jun 2025Mar 2025granted Jun 2025Jun 2025
Church Hill Farm, Church Hillsolar farmsolar farm0.8approved, not builtupdated Feb 2024Oct 2023granted Jan 2024Feb 2024
Burton Fleming Grange, Wold Newton Roadwind turbinewind turbine0.7approved, not builtupdated Sep 2023Apr 2023granted Aug 2023Sep 2023
Wingfield Wayrooftop solarrooftop solar0.6approved, not builtupdated Feb 2022Feb 2022granted Mar 2022Feb 2022
Tesco Distribution Centre. Tom Pudding Wayrooftop solarrooftop solar0.6approved, not builtupdated Nov 2025Jun 2025granted Jul 2025Nov 2025
Springdale Farm, High Streetrooftop solarrooftop solar0.5approved, not builtupdated May 2024Mar 2024granted May 2024May 2024
Raven Hill Farm, Langtoft Roadwind farmwind farm0.5approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025
Low Cowlam Farm, Driffield Roadwind farmwind farm0.5approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026
Great Kendale, Naffertonwind turbinewind turbine0.5approved, not builtupdated Mar 2026Dec 2025granted Jan 2026Mar 2026
Grove Farm, Main Streetwind farmwind farm0.5approved, not builtupdated Nov 2025Apr 2025granted Oct 2025Nov 2025
Middledale Heights, Langtoft Roadwind farmwind farm0.5approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025
Dalton Gates Farm, North Dalton Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2022Sep 2022granted Nov 2022Nov 2022
Bridlington And District Hospital, Bessingby Road Battery Unitbattery storagebattery storage0.4approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025
Thornwick Bay Holiday Village, North Marine Roadrooftop solarrooftop solar0.4approved, not builtupdated Jun 2023Mar 2023granted May 2023Jun 2023
Victory Conversions, Sandholme Business Parkrooftop solarrooftop solar0.4approved, not builtupdated Oct 2024Jul 2024granted Sep 2024Oct 2024
South Shore Holiday Villagesolar farmsolar farm0.4operationalupdated Mar 2023Jun 2019granted Dec 2020Mar 2023
Country Style Foods, Carnaby Industrial Estaterooftop solarrooftop solar0.4approved, not builtupdated Sep 2023Jul 2023granted Aug 2023Sep 2023
Rasher House, Catfoss Lanesolar farmsolar farm0.4approved, not builtupdated Jul 2026Apr 2026granted Jun 2026Jul 2026
Luxinar Limited, Rofin Houserooftop solarrooftop solar0.4approved, not builtupdated May 2023Feb 2023granted Apr 2023May 2023
Modular & Portable Buildings Hire Limited, Brandesburtonrooftop solarrooftop solar0.4approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023
Bessingby Roadsolar farmsolar farm0.4application submitted may be out of dateupdated May 2022Apr 2022—May 2022
Cottingham Water Pumping Station, Mill Housesolar farmsolar farm0.4approved, not builtupdated Oct 2023Jun 2023granted Sep 2023Oct 2023
Grange Farm, Finchcroft Lanesolar farmsolar farm0.4approved, not built may be out of dateupdated Aug 2023Apr 2023granted Jun 2023Aug 2023
Commons Farm, Thorne Roadsolar farmsolar farm0.4approved, not built may be out of dateupdated Aug 2023Jun 2023granted Jul 2023Aug 2023
Braffords Farm, Riplingham Roadwind turbinewind turbine0.3approved, not builtupdated Aug 2024Dec 2023granted Jul 2024Aug 2024
Newland Farm, Station Roadrooftop solarrooftop solar0.3application submittedupdated Sep 2024Aug 2024—Sep 2024
The Gardenssolar farmsolar farm0.3permission expiredupdated Mar 2020Dec 2019granted Nov 2020Mar 2020
St Helens Farm, Reangamoor Lanerooftop solarrooftop solar0.3approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025
Ryedale Farm, Seaton Common Lanerooftop solarrooftop solar0.3approved, not builtupdated Aug 2025Jul 2025granted Aug 2025Aug 2025
Withernsea High School, Hull Roadrooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026
A B Graphic International Limited , Wadsworth Roadrooftop solarrooftop solar0.3approved, not built may be out of dateupdated May 2023May 2023granted Jul 2023May 2023
Croda Europe, Tom Pudding Waysolar farmsolar farm0.3approved, not builtupdated Oct 2023Jun 2023granted Oct 2023Oct 2023
Spire Hospital, Lowfield Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted Apr 2024May 2024
Greenlands Farm, Barmby Moor Solar Photovoltaic Arraysrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025
Cold Harbour Farm, Cold Harbour Roadsolar farmsolar farm0.3approved, not builtupdated May 2024Dec 2023granted Apr 2024May 2024
Sand Le Mere Holiday Village, Southfield Lanerooftop solarrooftop solar0.3approved, not builtupdated Feb 2026Dec 2025granted Jan 2026Feb 2026
Melton Enterprise Park, Redcliff Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2026Dec 2025granted Feb 2026Apr 2026
Towthorpe Manor Farm, Towthorpe Roadwind turbinewind turbine0.2approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025
Market Weighton Road, Middleton On The Wolds -Wind Turbinewind turbinewind turbine0.2approved, not builtupdated Jan 2026Sep 2025granted Dec 2025Jan 2026
Weighton Wold, Arras Hillwind turbinewind turbine0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026
Cowden Magna Farm, Cowdenwind turbinewind turbine0.2approved, not builtupdated Jan 2026Nov 2025granted Jan 2026Jan 2026
Burton Roadwind turbinewind turbine0.2approved, not builtupdated Jan 2026Nov 2025granted Jan 2026Jan 2026
Burton Road, Burton Pidseawind turbinewind turbine0.2approved, not builtupdated May 2026Jan 2026granted Mar 2026May 2026
Priest Close, Burton Roadwind turbinewind turbine0.2approved, not builtupdated May 2026Feb 2026granted Mar 2026May 2026
Bessingby Roadrooftop solarrooftop solar0.2application submitted may be out of dateupdated May 2022Apr 2022—May 2022
Little Pockthorpe Farm, Pockthorpe Lanewind farmwind farm0.2approved, not builtupdated Nov 2025Apr 2025granted Jul 2025Nov 2025
Tuft Hill Farm, Woldgatewind turbinewind turbine0.2approved, not builtupdated Nov 2025Jun 2025granted Aug 2025Nov 2025
Weighton Road, Sanctonwind turbinewind turbine0.2approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026
Southfield House Farm, Hornsea Roadwind turbinewind turbine0.2application submittedupdated Feb 2026Jan 2026—Feb 2026
North Fordon Farm, Danebury Manor Roadwind turbinewind turbine0.2application submittedMay 2026——
Far Grange Caravan Park, Hornsea Roadrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023Mar 2023granted Apr 2023Jul 2023
The Oaks Golf Clubsolar farmsolar farm0.2approved, not built may be out of dateupdated Feb 2022Jan 2022granted Nov 2022Feb 2022
Wigwam Holidays Ball Hall Farm, Ballhall Lanesolar farmsolar farm0.2application submittedupdated May 2026Apr 2026—May 2026
B W Industries Limited, Carnaby Industrial Estaterooftop solarrooftop solar0.1approved, not builtupdated Jan 2025Sep 2024granted Nov 2024Jan 2025
Ferndale Park Newfields Industrial Estatebattery storagebattery storage—refusedupdated Nov 2018Oct 2017refused Jul 2018Nov 2018
Scurf Dyke Solar Farmbattery storagebattery storage—approved, not builtupdated Oct 2022Jan 2020granted Mar 2020Oct 2022
Old Chalk Pit, West Back Side - Three Oaks Renewable Parkbattery storagebattery storage—approved, not builtupdated Feb 2026Oct 2022granted Mar 2024Feb 2026
Ab Graphic International, Carnaby Industrial Estaterooftop solarrooftop solar—approved, not builtupdated Apr 2023Dec 2022granted Jan 2023Apr 2023
Bridlington Waste Water Treatment Workssolar farmsolar farm—approved, not builtupdated Sep 2023Jun 2023granted Aug 2023Sep 2023

8 more projects not listed (furthest or smallest).

Postcode districts in East Riding of Yorkshire

DistrictProjects within 10 kmPendingApprovedOperational
DN143531810
HU10503358
HU11422305
HU12262137
HU13472328
HU14321196
HU15171103
HU16552407
HU17361246
HU1811162
HU1912044
HU20291158
YO15162102
YO16202142
YO25170141
YO41221191
YO42173120
YO4313273

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to East Riding of Yorkshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.