Staithes Road, Saltend -Battery Energy Storage System (240 MW)

Staithes Road, Saltend -Battery Energy Storage System is a 240 MW battery storage project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 July 2025, not yet built; the record was last updated on 7 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

240 MWbattery storage
approved, not builtstatus in REPD
7 November 2025record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
16 December 2024Application submitted
21 July 2025Planning permission granted
21 July 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
240 MW
Status (REPD)
approved, not built
Record last updated
7 November 2025
Operator or applicant
SFEL One Limited
Planning authority
East Riding of Yorkshire
Planning application reference
24/03387/STPLF
Address (REPD)
North Of Westfield View Staithes Road Preston
Council area (by location)
East Riding of Yorkshire
Time to decision
31 weeks
REPD reference
17842

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Neat Marsh North, Neat Marsh Road Solar Farmsolar farm49.9approved, not built1.1
Kingston International Business Parkbattery storage200approved, not built1.5
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagesolar farm49.9approved, not built1.6
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagebattery storage20approved, not built1.6
Salt End Lanebattery storage49permission expired2.5
Harbour Farm Solar Farmsolar farm42application submitted2.5
Hull Solar Farmsolar farm25.7under construction2.6
Green Frog Power, Great Field Lanebattery storage20approved, not built2.8
Hull East Stor Generation Compoundbattery storage20approved, not built2.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7563, -0.2124).