Harbour Farm Solar Farm (42 MW)

Harbour Farm Solar Farm is a 42 MW solar farm project in East Riding of Yorkshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 17 September 2025, no decision recorded; the record was last updated on 17 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

42 MWsolar farm
application submittedstatus in REPD
17 October 2025record last updated
East Riding of Yorkshirecouncil area

Planning timeline

DateStage
17 September 2025Application submitted

Project details

Technology
solar farm
Capacity
42 MW
Status (REPD)
application submitted
Record last updated
17 October 2025
Operator or applicant
Grupotec
Planning authority
East Riding of Yorkshire
Planning application reference
25/02255/STPLFE
Site area
61.9 ha
Address (REPD)
Harbour Farm Havenside Hedon
Council area (by location)
East Riding of Yorkshire
Name in REPD
Harbour Farm - Solar Farm
REPD reference
11386

Who decides

ApplicationsEast Riding of YorkshireUK
Decided applications (solar, wind, battery)14310,236
Refused26 (18%)19%
Solar refused1 of 5912%
Onshore wind refused24 of 6345%
Battery storage refused1 of 2116%
Median time from submission to decision18.9 weeks17.0 weeks
Appeals lodged / allowed4 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kingston International Business Parkbattery storage200approved, not built2.3
Salt End Lanebattery storage49permission expired2.3
Staithes Road, Saltend -Battery Energy Storage Systembattery storage240approved, not built2.5
Neat Marsh North, Neat Marsh Road Solar Farmsolar farm49.9approved, not built3.1
Green Frog Power, Great Field Lanebattery storage20approved, not built3.5
Hull East Stor Generation Compoundbattery storage20approved, not built3.8
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagesolar farm49.9approved, not built4.0
Froghall Farm, Wyton Road Solar Farm & Battery Energy Storagebattery storage20approved, not built4.0
Elstronwick, Burstwick - Daisy Hill Solar Photovoltaic Farmsolar farm35approved, not built4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (53.7345, -0.2023).